Common use of Format of Applications Clause in Contracts

Format of Applications. 5.2.1.1 On or before the first (1st) day of each month, Contractor shall submit to Owner and Owner’s Lenders an initial draft of Contractor’s Application for Progress Payment for the previous month. 5.2.1.2 On or before the fifth (5th) day of each month, Contractor shall submit to Owner and Owner’s Lenders a fully completed Application For Progress Payment for the previous month in a format reasonably satisfactory to Owner and supported by such documentation to verify entitlement as Owner and Owner’s Lenders may reasonably require, and certified by Contractor as correct. Each Application for Progress Payment shall be sequentially numbered, and shall clearly identify, itemize and attribute all Costs of the Work in a manner which facilitates review by Owner. Such Applications for Progress Payment may only request payment for Costs of the Work actually incurred prior to the date of such Application for Progress Payment and may not include requests for payment of amounts Contractor does not intend to pay promptly to a Subcontractor or Vendor because of a dispute or other reason. Contractor shall not submit more than one Application for Progress Payment per month, unless otherwise requested by Owner. In addition, each Application for Progress Payment shall separately identify and itemize the following: (a) Work performed during such preceding calendar month. (b) Amounts due for Contractor’s initial scope of Work satisfactorily completed during the preceding month as measured by the Contractor’s direct and actual costs incurred in accordance with the Cost of the Work described in Section 3.2 of this Agreement, a list of all bills for supplies, materials, equipment, and fixtures incorporated in the Work (in detail reasonably sufficient to allow Owner to determine where each item is incorporated) and labor performed (in detail reasonably sufficient to allow Owner to determine where and on what portion of the Work the labor was performed, including, but not limited to, weekly labor payrolls with names, dates, hours and rates) in connection with the Work, together with copies of the actual bills to be paid. (c) For each category and portion of the Work as shown on the Schedule of Values: (1) the amount requested on all previous Applications for Progress Payment, (2) the amount requested on the current Application for Progress Payment, and (3) the amount allocated to the Work yet to be completed. (d) The percentage completion of each portion of the Work as of the end of the period covered by the Application for Progress Payment, shown as the percentage obtained by dividing (a) the expense which has actually been incurred by Contractor on account of that portion of the Work for which Contractor has made or intends to make actual payment prior to the next Application for Progress Payment, by (b) the amount allocated to that portion of the Work in the Schedule of Values. (e) Amounts due which are attributable to the Contractor’s Fee earned as a result of the completion of Contractor’s scope of Work during such period covered by and included in the Application for Progress and approved by Owner. Under no circumstances shall Contractor include in any Application for Progress Payment, nor shall Owner be required to pay, an Application for Progress Payment for funds to pay an amount in excess of the then applicable pro rata portion of the Contractor’s Fee, using the ratio that the portion of the Work then completed bears to the total Work (as determined by the total Costs of the Work disbursed to date compared to the total approved Costs of the Work amount on the Schedule of Values). (f) For all amounts due as the result of Change Orders and Construction Change Directives, the Contractor shall make submittals for each Change Order and Construction Change Directive. (g) Reflect Retainage in the amount provided for pursuant to Section 5.6 of this Agreement. (h) Such additional information and documentation regarding the progress of the Work as Owner or Owner’s Lenders may reasonably require.

Appears in 2 contracts

Samples: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc)

AutoNDA by SimpleDocs

Format of Applications. 5.2.1.1 On or before the first (1st) day of each month, Contractor shall submit to Owner and Owner’s 's Lenders an initial draft of Contractor’s 's Application for Progress Payment for the previous month. 5.2.1.2 On or before the fifth (5th) day of each month, Contractor shall submit to Owner and Owner’s 's Lenders a fully completed Application For Progress Payment for the previous month in a format reasonably satisfactory to Owner and supported by such documentation to verify entitlement as Owner and Owner’s 's Lenders may reasonably require, and certified by Contractor as correct. Each Application for Progress Payment shall be sequentially numbered, and shall clearly identify, itemize and attribute all Costs of the Work in a manner which facilitates review by Owner. Such Applications for Progress Payment may only request payment for Costs of the Work actually incurred prior to the date of such Application for Progress Payment and may not include requests for payment of amounts Contractor does not intend to pay promptly to a Subcontractor or Vendor because of a dispute or other reason. Contractor shall not submit more than one Application for Progress Payment per month, unless otherwise requested by Owner. In addition, each Application for Progress Payment shall separately identify and itemize the following: (a) Work performed during such preceding calendar month. (b) Amounts due for Contractor’s 's initial scope of Work satisfactorily completed during the preceding month as measured by the Contractor’s 's direct and actual costs incurred in accordance with the Cost of the Work described in Section 3.2 of this Agreement, a list of all bills for supplies, materials, equipment, and fixtures incorporated in the Work (in detail reasonably sufficient to allow Owner to determine where each item is incorporated) and labor performed (in detail reasonably sufficient to allow Owner to determine where and on what portion of the Work the labor was performed, including, but not limited to, weekly labor payrolls with names, dates, hours and rates) in connection with the Work, together with copies of the actual bills to be paid. (c) For each category and portion of the Work as shown on the Schedule of Values: (1) the amount requested on all previous Applications for Progress Payment, (2) the amount requested on the current Application for Progress Payment, and (3) the amount allocated to the Work yet to be completed. (d) The percentage completion of each portion of the Work as of the end of the period covered by the Application for Progress Payment, shown as the percentage obtained by dividing (a) the expense which has actually been incurred by Contractor on account of that portion of the Work for which Contractor has made or intends to make actual payment prior to the next Application for Progress Payment, by (b) the amount allocated to that portion of the Work in the Schedule of Values. (e) Amounts due which are attributable to the Contractor’s 's Fee earned as a result of the completion of Contractor’s 's scope of Work during such period covered by and included in the Application for Progress and approved by Owner. Under no circumstances shall Contractor include in any Application for Progress Payment, nor shall Owner be required to pay, an Application for Progress Payment for funds to pay an amount in excess of the then applicable pro rata portion of the Contractor’s 's Fee, using the ratio that the portion of the Work then completed bears to the total Work (as determined by the total Costs of the Work disbursed to date compared to the total approved Costs of the Work amount on the Schedule of Values). (f) For all amounts due as the result of Change Orders and Construction Change Directives, the Contractor shall make submittals for each Change Order and Construction Change Directive. (g) Reflect Retainage in the amount provided for pursuant to Section 5.6 of this Agreement. (h) Such additional information and documentation regarding the progress of the Work as Owner or Owner’s 's Lenders may reasonably require.

Appears in 1 contract

Samples: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)

Format of Applications. 5.2.1.1 On or before the first (1st) day of each month, Contractor shall submit to Owner and Owner’s Lenders an initial draft of Contractor’s Application for Progress Payment for the previous month. 5.2.1.2 On or before the fifth (5th) day of each month, Contractor shall submit to Owner and Owner’s Lenders a fully completed Application For Progress Payment for the previous month in a format reasonably satisfactory to Owner and supported by such documentation to verify entitlement as Owner and Owner’s Lenders may reasonably require, and certified by Contractor as correct. Each Application for Progress Payment shall be sequentially numbered, and shall clearly identify, itemize and attribute all Costs of the Work in a manner which facilitates review by Owner. Such Applications for Progress Payment may only request payment for Costs Cost of the Work actually incurred prior to the date of such Application for Progress Payment and that the Contractor has paid or intends to pay to a Subcontractor or Vendor promptly after receipt by the Contractor of the corresponding payment from the Owner, and may not include requests for payment of amounts Contractor does not intend to pay promptly to a Subcontractor or Vendor because of a dispute or other reason. Contractor shall not submit more than one Application for Progress Payment per month, unless otherwise requested by Owner. In addition, each Application for Progress Payment shall separately identify and itemize the following: (a) Work performed during such preceding calendar month, together with a statement indicating what portion of such Work relates to the Hotel or the Casino, respectively. (b) Amounts due for Contractor’s initial scope of Work satisfactorily completed during the preceding month as measured by the Contractor’s direct and actual costs incurred in accordance with the Cost of the Work described in Section 3.2 of this Agreement, a list of all bills for supplies, materials, equipment, and fixtures incorporated or to be incorporated in the Work (in detail reasonably sufficient to allow Owner to determine where each item is incorporated or to be incorporated) and labor performed (in detail reasonably sufficient to allow Owner to determine where and on what portion of the Work the labor was performed, including, but not limited to, weekly labor payrolls with names, dates, hours and rates) in connection with the Work, together with copies of the actual bills payable to be paidSubcontractors and Vendors under lump sum agreements or otherwise as they relate to such Application for Payment. (c) For each category and portion of the Work as shown on the Schedule of Values: (1) the amount requested on all previous Applications for Progress Payment, (2) the amount requested on the current Application for Progress Payment, and (3) the amount allocated to the Work yet to be completed. (d) The percentage completion of each portion of the Work as of the end of the period covered by the Application for Progress Payment, shown as the percentage obtained by dividing (a) the expense which has actually been incurred by Contractor on account of that portion of the Work for which Contractor has made or intends to make actual payment prior to the next Application for Progress Payment, by (b) the amount allocated to that portion of the Work in the Schedule of Values. (e) Amounts due which are attributable to the Contractor’s Fee earned as a result of the completion of Contractor’s scope of Work during such period covered by and included in the Application for Progress Payment and approved by Owner. Under no circumstances shall Contractor include in any Application for Progress Payment, nor shall Owner be required to pay, an Application for Progress Payment for funds to pay an amount in excess of the then applicable pro rata portion of the Contractor’s Fee, using the ratio that the portion of the Work then completed bears to the total Work (as determined by the total Costs of the Work disbursed to date compared to the total approved Costs of the Work amount on the Schedule of Values). (f) For all amounts due as the result of Change Orders and Construction Change Directives, the Contractor shall make submittals for each Change Order and Construction Change Directive. (g) Reflect Retainage Retention in the amount provided for pursuant to Section 5.6 of this Agreement. (h) Such additional information and documentation regarding the progress of the Work as Owner or Owner’s Lenders may reasonably require.

Appears in 1 contract

Samples: Design Build Agreement (Wynn Resorts LTD)

AutoNDA by SimpleDocs

Format of Applications. 5.2.1.1 On or before the first (1st) day of each month, Contractor shall submit to Owner and Owner’s Lenders an initial draft of a Contractor’s Application for Progress Payment for the previous monthmonth itemized with respect to Original Project Work and Expansion Project Work. 5.2.1.2 On or before the fifth (5th) day of each month, Contractor shall submit to Owner and Owner’s Lenders a fully completed Application Applications For Progress Payment for Original Project Work and Expansion Project Work for the previous month in a format reasonably satisfactory to Owner and supported by such documentation to verify entitlement as Owner and Owner’s Lenders may reasonably require, and certified by Contractor as correct. Each Application for Progress Payment Payment, identified as a Original Project Work application or a Expansion Project Work application, shall be separately and sequentially numberednumbered by Original Project Work or Expansion Project Work, and shall clearly identify, itemize and attribute all Costs of the Work in a manner which facilitates review by Owner. Such Applications for Progress Payment may only request payment for Costs Cost of the Work actually incurred prior to the date of such Application for Progress Payment and that the Contractor has paid or intends to pay to a Subcontractor or Vendor promptly after receipt by the Contractor of the corresponding payment from the Owner, and may not include requests for payment of amounts Contractor does not intend to pay promptly to a Subcontractor or Vendor because of a dispute or other reason. Contractor shall not submit more than one Application for Progress Payment per Original Project Work or Expansion Project Work per month, unless otherwise requested by Owner. In addition, each Application for Progress Payment shall separately identify and itemize the following: (a) Work performed during such preceding calendar month, together with a statement indicating what portion of such Work relates to the Hotel or the Casino, respectively. (b) Amounts due for Contractor’s initial scope of Work satisfactorily completed during the preceding month as measured by the Contractor’s direct and actual costs incurred in accordance with the Cost of the Work described in Section 3.2 of this Agreement, a list of all bills for supplies, materials, equipment, and fixtures incorporated or to be incorporated in the Work (in detail reasonably sufficient to allow Owner to determine where each item is incorporated or to be incorporated) and labor performed (in detail reasonably sufficient to allow Owner to determine where and on what portion of the Work the labor was performed, including, but not limited to, weekly labor payrolls with names, dates, hours and rates) in connection with the Work, together with copies of the actual bills payable to be paidSubcontractors and Vendors under lump sum agreements or otherwise as they relate to such Application for Payment. (c) For each category and portion of the Work as shown on the Original Project Schedule of Values: Approved Values or Expansion Project Schedule of Values (as applicable): (1) the amount requested on all previous Applications for Progress Payment, (2) the amount requested on the current Application for Progress Payment, and (3) the amount allocated to the Work yet to be completed. (d) The percentage completion of each portion of the Work as of the end of the period covered by the Application for Progress Payment, shown as the percentage obtained by dividing (a) the expense which has actually been incurred by Contractor on account of that portion of the Work for which Contractor has made or intends to make actual payment prior to the next Application for Progress Payment, by (b) the amount allocated to that portion of the Work in the Original Project Schedule of ValuesApproved Values or Expansion Project Schedule of Values (as applicable). (e) Amounts due which are attributable to the Original Project Contractor’s Fee or Expansion Project Contractor’s Fee (as applicable) earned as a result of the completion of Contractor’s scope of Work during such period covered by and included in the Application for Progress Payment and approved by Owner. Under no circumstances shall Contractor include in any Application for Progress Payment, nor shall Owner be required to pay, an Application for Progress Payment for funds to pay an amount in excess of the then applicable pro rata portion of the Original Project Contractor’s FeeFee or Expansion Project Contractor’s Fee (as applicable), using the ratio that the portion of the Work then completed bears to the total Work (as determined by the total Costs of the Work disbursed to date for the Original Project Work or Expansion Project Work (as applicable) compared to the total approved Costs of the Work amount on the Original Project Schedule of ValuesApproved Values or Expansion Project Schedule of Values (as applicable)). (f) For all amounts due as the result of Change Orders and Construction Change Directives, the Contractor shall make submittals for each Change Order and Construction Change Directive. (g) Reflect Retainage Retention in the amount provided for pursuant to Section 5.6 of this Agreement. (h) Such additional information and documentation regarding the progress of the Work as Owner or Owner’s Lenders may reasonably require.

Appears in 1 contract

Samples: Design Build Agreement (Wynn Resorts LTD)