Common use of FUEL PRICE ADJUSTMENT Clause in Contracts

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 2 contracts

Samples: Roadway Contract, Roadway Contract

AutoNDA by SimpleDocs

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0345 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 2016 (7/01/16 7/01/15 - 6/30/176/30/16) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19100 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 2 contracts

Samples: Roadway Contract, Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.8075 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2019 (7/01/18 - 6/30/176/30/19) 8130% of Total Amount Bid 2018 2020 (7/01/17 7/01/19 - 6/30/186/30/20) 1970% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.7405 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 2016 (7/01/16 7/01/15 - 6/30/176/30/16) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19100 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.1131 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2016 (7/01/15 - 6/30/16) 20 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1980 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.2917 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8193 % of Total Amount Bid 2018 (7/01/17 - 6/30/18) 197 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract and Contract Bonds

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0345 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2016 (7/01/15 - 6/30/16) 85 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1915 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0853 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2020 (7/01/19 - 6/30/176/30/20) 8159% of Total Amount Bid 2018 2021 (7/01/17 7/01/20 - 6/30/186/30/21) 1936% of Total Amount Bid 2022 (7/01/21 - 6/30/22) 5% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5950 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8164% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1936% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0538 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1720-1614) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 2015 (7/01/16 7/01/14 - 6/30/176/30/15) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19100 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.6338 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8139% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1961% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.3531 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1713-1619) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2021 (7/01/20 - 6/30/176/30/21) 8153% of Total Amount Bid 2018 2022 (7/01/17 7/01/21 - 6/30/186/30/22) 1944% of Total Amount Bid 2023 (7/01/22 - 6/30/23) 3% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0412 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2019 (7/01/18 - 6/30/176/30/19) 8127% of Total Amount Bid 2018 2020 (7/01/17 7/01/19 - 6/30/186/30/20) 1965% of Total Amount Bid 2021 (7/01/20 - 6/30/21) 8% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.2375 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2019 (7/01/18 - 6/30/176/30/19) 8177% of Total Amount Bid 2018 2020 (7/01/17 7/01/19 - 6/30/186/30/20) 1923% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5868 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19100% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 0.9532 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2016 (7/01/15 - 6/30/16) 18 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 8174 % of Total Amount Bid 2018 (7/01/17 - 6/30/18) 198 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.7230 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 812% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1943% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 32% of Total Amount Bid 2020 (7/01/19 - 6/30/20) 17% of Total Amount Bid 2021 (7/-1/20 – 6/30/21) 6% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Construction Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.6823 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1980% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 20% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.6936 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8125% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1966% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 9% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.5028 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1720-1614) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2015 (7/01/14 - 6/30/15) 19 % of Total Amount Bid 2016 (7/01/15 - 6/30/16) 49 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 8129 % of Total Amount Bid 2018 (7/01/17 - 6/30/18) 193 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5065 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2016 (7/01/15 - 6/30/16) 80 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1920 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Construction Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.9515 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2020 (7/01/19 - 6/30/176/30/20) 8139% of Total Amount Bid 2018 2021 (7/01/17 7/01/20 - 6/30/186/30/21) 1940% of Total Amount Bid 2022 (7/01/21 - 6/30/22) 21% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.6237 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8161% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1939% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

AutoNDA by SimpleDocs

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5868 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8156 % of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1940 % of Total Amount Bid 2019 (7/01/18 – 6/30/19) 4 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 $0.9532 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1719-1615) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2016 (7/01/15 - 6/30/16) 16 % of Total Amount Bid 2017 (7/01/16 - 6/30/17) 8173 % of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1911 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0853 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2020 (7/01/19 - 6/30/176/30/20) 8186% of Total Amount Bid 2018 2021 (7/01/17 7/01/20 - 6/30/186/30/21) 1914% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8149% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1943% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 8% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.2154 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2019 (7/01/18 - 6/30/176/30/19) 8187% of Total Amount Bid 2018 2020 (7/01/17 7/01/19 - 6/30/186/30/20) 1913% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5765 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 192% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 98% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.9815 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 - 6/30/17) 81% of Total Amount Bid Dollar Value) 2018 (7/01/17 - 6/30/18) 1920% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 75% of Total Amount Bid 2020 (7/01/19 - 6/30/20) 5% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer. (10-16-07)(Rev.1-17-17) 102-15(J) SP1 G62 The purpose of this Special Provision is to carry out the U.S. Department of Transportation’s policy of ensuring nondiscrimination in the award and administration of contracts financed in whole or in part with Federal funds. This provision is guided by 49 CFR Part 26. Additional DBE Subcontractors - Any DBE submitted at the time of bid that will not be used to meet the DBE goal. No submittal of a Letter of Intent is required.

Appears in 1 contract

Samples: Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.4426 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 2018 (7/01/16 7/01/17 - 6/30/176/30/18) 81% of Total Amount Bid 2018 2019 (7/01/17 7/01/18 - 6/30/186/30/19) 19% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.2154 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 56-1719-1618) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2019 (7/01/18 - 6/30/176/30/19) 8187 % of Total Amount Bid 2018 2020 (7/01/17 - 6/30/187/01/19 – 6/30/20) 1913 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 2.0538 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1720-1614) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 2015 (7/01/16 7/01/14 - 6/30/176/30/15) 8126 % of Total Amount Bid 2018 2016 (7/01/17 7/01/15 - 6/30/186/30/16) 1974 % of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 2018 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.8495 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-1713-1619) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 % of Dollar Value) 2020 (7/01/19 - 6/30/176/30/20) 8124% of Total Amount Bid 2018 2021 (7/01/17 7/01/20 - 6/30/186/30/21) 1975% of Total Amount Bid 2022 (7/01/21 - 6/30/22) 1% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 2018 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway & Structure Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.7069 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 Fiscal Year Progress (7/01/16 - 6/30/17) 81% of Total Amount Bid Dollar Value) 2018 (7/01/17 - 6/30/18) 1930% of Total Amount Bid 2019 (7/01/18 - 6/30/19) 67% of Total Amount Bid 2020 (7/01/19 - 6/30/20) 3% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.5601 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 8164% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 1936% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

FUEL PRICE ADJUSTMENT. (11-15-05) (Rev. 2-18-14) 109-8 SP1 G43 Revise the 2012 Standard Specifications as follows: The base index price for DIESEL #2 FUEL is $ 1.5593 1.6823 per gallon. Where any of the following are included as pay items in the contract, they will be eligible for fuel price adjustment. The pay items and the fuel factor used in calculating adjustments to be made will be as follows: Unclassified Excavation Gal/CY 0.29 Borrow Excavation Gal/CY 0.29 Class IV Subgrade Stabilization Gal/Ton 0.55 Aggregate Base Course Gal/Ton 0.55 Sub-Ballast Gal/Ton 0.55 Asphalt Concrete Base Course, Type Gal/Ton 2.90 Asphalt Concrete Intermediate Course, Type _ Gal/Ton 2.90 Asphalt Concrete Surface Course, Type Gal/Ton 2.90 Open-Graded Asphalt Friction Course Gal/Ton 2.90 Permeable Asphalt Drainage Course, Type Gal/Ton 2.90 Sand Asphalt Surface Course, Type Gal/Ton 2.90 Aggregate for Cement Treated Base Course Gal/Ton 0.55 Portland Cement for Cement Treated Base Course Gal/Ton 0.55 " Portland Cement Concrete Pavement Gal/SY 0.245 Concrete Shoulders Adjacent to " Pavement Gal/SY 0.245 (7-15-08) (Rev. 5-16-17-16) 108-2 SP1 G58 The Contractor's attention is directed to the Standard Special Provision entitled Availability of Funds Termination of Contracts included elsewhere in this proposal. The Department of Transportation's schedule of estimated completion progress for this project as required by that Standard Special Provision is as follows: 2017 (7/01/16 - 6/30/17) 81% of Total Amount Bid 2018 (7/01/17 - 6/30/18) 19100% of Total Amount Bid The Contractor shall also furnish his own progress schedule in accordance with Article 108-2 of the 2012 Standard Specifications. Any acceleration of the progress as shown by the Contractor's progress schedule over the progress as shown above shall be subject to the approval of the Engineer.

Appears in 1 contract

Samples: Roadway Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!