Common use of GUARANTEED COMPLETION DATE Clause in Contracts

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27, 2019, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two Thousand Five Hundred and No One-Hundredth Dollars ($2,500) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Design Build Services Contract

AutoNDA by SimpleDocs

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27May 29, 20192025, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two Three Thousand Five Hundred and No One-One Hundredth Dollars ($2,5003,500) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Contract for Design Build Services

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder Contractor will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder Contractor will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27March 26, 20192025, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder Contractor or the Design-BuilderContractor’s Surety, the Owner may retain the sum of Two Thousand Five Hundred and No One-Hundredth Dollars ($2,500500.00) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates. The maximum amount of liquidated damages shall not exceed 10% of the Contract Sum.

Appears in 1 contract

Samples: Contract for Services

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27November 18, 20192021, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two One Thousand Five Nine Hundred and No One-Hundredth Dollars ($2,5001,900) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Contract for Design Build Services

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27November 16, 20192020, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two Thousand Five One Hundred and No One-One Hundredth Dollars ($2,5002,100) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Contract for Design Build Services

AutoNDA by SimpleDocs

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27November 15, 20192018, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two Thousand Five Hundred and No One-Hundredth Dollars ($2,500500.00) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Design Build Services Contract

GUARANTEED COMPLETION DATE. 23.1 The Design-Builder will commence the Work within 10 days of the date set by the Owner in a written Notice to Proceed. The Design-Builder will achieve Substantial Completion of the Work no later than the Guaranteed Completion Date of September 27December 29, 20192022, subject to authorized adjustments and in accordance with the Contract Documents. 23.2 It is mutually agreed between the parties hereto that time is of the essence of this Contract and in the event the Work has not achieved Substantial Completion by the Guaranteed Completion Date herein specified, it is agreed that from any money due or to become due the Design-Builder or the Design-Builder’s Surety, the Owner may retain the sum of Two Thousand Five Four Hundred and No One-One Hundredth Dollars ($2,5002,400.00) per day, for each day thereafter, Sundays and holidays included, until the Work is substantially completed, not as a penalty but as liquidation of a reasonable portion of loss that will be incurred by the Owner if Work is not completed on or before the Guaranteed Completion Date. Multiple Substantial Completion Dates may be defined as part of this Contract. In addition, the Owner may retain different sums as liquidated damages if Work is not completed on or before the Substantial Completion Dates.

Appears in 1 contract

Samples: Contract for Design Build Services