Implementation Action Plan. 5.1 Detailed technical description for implementation of each recommended Measure: 5.1.1 Specifications suitable for procurement of bids for the Project construction and commissioning. Include sample manufacturers data sheets if applicable, 5.1.2 List of existing equipment to be de-commissioned, 5.1.3 Proposed operating parameters including mode and sequence of operation and programming of process control systems. 5.2 Provide a schedule for implementation: 5.2.1 Overall time to complete Project broken down by major tasks and time required for each, 5.2.2 Detail any known timeline risks and critical tasks.
Appears in 3 contracts
Samples: Detailed Engineering Study Funding Contract, Detailed Engineering Study Funding Contract, Detailed Engineering Study Funding Contract
Implementation Action Plan. 5.1 Detailed technical description for implementation of each recommended Measure:
5.1.1 Specifications suitable for procurement of bids for the Project construction and commissioning. Include sample manufacturers data sheets if applicable,
5.1.2 List of existing equipment to be de-commissioned,
5.1.3 Proposed operating parameters including mode and sequence of operation and programming of process control systems.
5.2 Provide a schedule for implementation:
5.2.1 Overall time to complete Project broken down by major tasks and time required for each,
5.2.2 Detail any known timeline risks and critical tasks.. DETAILED ENGINEERING STUDY SOW ELIGIBILITY CRITERIA