IMPROVEMENTS COMPLETION DATE Sample Clauses

IMPROVEMENTS COMPLETION DATE. Applicant shall complete the Improvements within a period of one year from the date of the City land use approval for the Project.
IMPROVEMENTS COMPLETION DATE. No later than Ten (10) years after the Closing Date (the “Improvements Completion Date”) there shall be Final Completion of the Improvements in accordance with the Requirements, subject to Unavoidable Delays. In the event of any extension(s) hereunder of the Improvements Completion Date for reason of one or more events of Unavoidable Delay, however, the period of extension (considered cumulatively and in the aggregate for all such events of Unavoidable Delay), shall not exceed twelve (12) months.
IMPROVEMENTS COMPLETION DATE. The later of the date on which the Owner is issued a Certificate of Occupancy or an approved final inspection by the City with respect to the Improvements.
IMPROVEMENTS COMPLETION DATE. The Applicant shall complete the Improvements within 6 months (maximum 6 months) of the Effective Date.