Common use of Inability by VicForests to Provide Access Clause in Contracts

Inability by VicForests to Provide Access. (a) If VicForests is unable to provide the Contractor with access to Harvest Sites scheduled in the Monthly Plan, VicForests shall estimate the quantity of Timber it has not made available to the Contractor or that the Contractor has not been able to harvest based on the Annual Plan (Shortfall) and if reasonably practicable add that Shortfall to subsequent Monthly Quantities.

Appears in 4 contracts

Samples: Harvest Agreement, www.vicforests.com.au, www.vicforests.com.au

AutoNDA by SimpleDocs

Inability by VicForests to Provide Access. (a) If VicForests is unable to provide the Contractor with access to Harvest Sites and/or Delivery Sites scheduled in the Monthly Plan, VicForests shall estimate the quantity of Timber it has not made available to the Contractor or that the Contractor has (and where applicable, pursuant to Schedule 7, an Other Contractor) have not been able to harvest haul based on the Annual Plan (Shortfall) and if reasonably practicable add that Shortfall to subsequent Monthly Quantities.

Appears in 2 contracts

Samples: www.vicforests.com.au, www.vicforests.com.au

Inability by VicForests to Provide Access. (a) If VicForests is unable to provide the Contractor with access to Harvest Sites and/or Delivery Sites scheduled in the Monthly Plan, VicForests shall estimate the quantity of Timber it has not made available to the Contractor or that the Contractor has (and where applicable, pursuant to Schedule 6, an Other Contractor) have not been able to harvest haul based on the Annual Plan (Shortfall) and if reasonably practicable add that Shortfall to subsequent Monthly Quantities.

Appears in 2 contracts

Samples: www.vicforests.com.au, www.vicforests.com.au

AutoNDA by SimpleDocs

Inability by VicForests to Provide Access. (a) If VicForests is unable to provide the Contractor with access to Harvest Sites and/or Delivery Sites scheduled in the Monthly Plan, VicForests shall estimate the quantity of Timber it has not made available to the Contractor or that the Contractor has not been able to harvest and haul (or arrange for an Other Contractor to haul) based on the Annual Plan (Shortfall) and if reasonably practicable add that Shortfall to subsequent Monthly Quantities.

Appears in 1 contract

Samples: www.vicforests.com.au