Common use of Inability to Timely Restore; Estimate of Time and Cost to Restore Clause in Contracts

Inability to Timely Restore; Estimate of Time and Cost to Restore. (a) The determination of the estimated time and costs that are reasonably expected to be necessary to perform and substantially complete any Condemnation Restoration Work or any Casualty Restoration Work shall be made by an independent architect or construction manager that is experienced in arena construction projects, well-regarded in the industry and selected by Licensor and reasonably approved by the Knicks. In the event of any Condemnation or Casualty resulting in an Untenantable Condition, Licensor shall furnish to the Knicks an estimate (the “Estimate”), prepared and certified by such independent architect or construction manager (the “Estimator”) of (i) the estimated date (the “Estimated Date”) by which the Condemnation Restoration Work or Casualty Restoration Work, as the case may be, will be substantially completed and (ii) the estimated cost (the “Estimated Restoration Cost”) to perform the Condemnation Restoration Work or Casualty Restoration Work, as the case may be. Licensor shall use commercially reasonable efforts to cause such independent architect or construction manager to make its determination as soon as reasonably practicable (and, in the case of a Casualty, no later than [*****] after the date of such Casualty) and will deliver the Estimate to the Knicks promptly upon Licensor’s receipt thereof. (b) (i) If, during the performance of the Condemnation Restoration Work or the Casualty Restoration Work required as a result of any Condemnation or Casualty, the Knicks reasonably believe that the substantial completion of such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, will not, absent extraordinary efforts that Licensor does not agree (if not already obligated to take pursuant to this Agreement), be achieved by the applicable Condemnation Outside Date or applicable Casualty Outside Date therefor (as such Condemnation Outside Date or such Casualty Outside Date may have theretofore been postponed pursuant to the provisions of Section 12.01(d) or Section 12.02(d) above, respectively), then the Knicks, by notice given to Licensor and the Estimator, shall have the right (not to be exercised more than once in any six (6) month period) with respect to such Condemnation or such Casualty to request that the Estimator determine the estimated date (the “Revised Estimated Date”) by which such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, is then reasonably expected to be substantially completed.

Appears in 5 contracts

Samples: Arena License Agreement (Madison Square Garden Sports Corp.), Arena License Agreement (Madison Square Garden Entertainment Corp.), License Agreement (Madison Square Garden Co)

AutoNDA by SimpleDocs

Inability to Timely Restore; Estimate of Time and Cost to Restore. (a) The determination of the estimated time and costs that are reasonably expected to be necessary to perform and substantially complete any Condemnation Restoration Work or any Casualty Restoration Work shall be made by an independent architect or construction manager that is experienced in arena construction projects, well-regarded in the industry and selected by Licensor and reasonably approved by the KnicksRangers. In the event of any Condemnation or Casualty resulting in an Untenantable Condition, Licensor shall furnish to the Knicks Rangers an estimate (the “Estimate”), prepared and certified by such independent architect or construction manager (the “Estimator”) of (i) the estimated date (the “Estimated Date”) by which the Condemnation Restoration Work or Casualty Restoration Work, as the case may be, will be substantially completed and (ii) the estimated cost (the “Estimated Restoration Cost”) to perform the Condemnation Restoration Work or Casualty Restoration Work, as the case may be. Licensor shall use commercially reasonable efforts to cause such independent architect or construction manager to make its determination as soon as reasonably practicable (and, in the case of a Casualty, no later than [*****] after the date of such Casualty) and will deliver the Estimate to the Knicks Rangers promptly upon Licensor’s receipt thereof. (b) (i) If, during the performance of the Condemnation Restoration Work or the Casualty Restoration Work required as a result of any Condemnation or Casualty, the Knicks Rangers reasonably believe that the substantial completion of such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, will not, absent extraordinary efforts that Licensor does not agree (if not already obligated to take pursuant to this Agreement), be achieved by the applicable Condemnation Outside Date or applicable Casualty Outside Date therefor (as such Condemnation Outside Date or such Casualty Outside Date may have theretofore been postponed pursuant to the provisions of Section 12.01(d) or Section 12.02(d) above, respectively), then the KnicksRangers, by notice given to Licensor and the Estimator, shall have the right (not to be exercised more than once in any six (6) month period) with respect to such Condemnation or such Casualty to request that the Estimator determine the estimated date (the “Revised Estimated Date”) by which such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, is then reasonably expected to be substantially completed.

Appears in 5 contracts

Samples: Arena License Agreement (Madison Square Garden Co), Arena License Agreement (MSG Entertainment Spinco, Inc.), Arena License Agreement (MSG Entertainment Spinco, Inc.)

AutoNDA by SimpleDocs

Inability to Timely Restore; Estimate of Time and Cost to Restore. (a) The determination of the estimated time and costs that are reasonably expected to be necessary to perform and substantially complete any Condemnation Restoration Work or any Casualty Restoration Work shall be made by an independent architect or construction manager that is experienced in arena construction projects, well-regarded in the industry and selected by Licensor and reasonably approved by the Knicks. In the event of any Condemnation or Casualty resulting in an Untenantable Condition, Licensor shall furnish to the Knicks an estimate (the “Estimate”), prepared and certified by such independent architect or construction manager (the “Estimator”) of (i) the estimated date (the “Estimated Date”) by which the Condemnation Restoration Work or Casualty Restoration Work, as the case may be, will be substantially completed and (ii) the estimated cost (the “Estimated Restoration Cost”) to perform the Condemnation Restoration Work or Casualty Restoration Work, as the case may be. Licensor shall use commercially reasonable efforts to cause such independent architect or construction manager to make its determination as soon as reasonably practicable (and, in the case of a Casualty, no later than [*****] sixty (60) days after the date of such Casualty) and will deliver the Estimate to the Knicks promptly upon Licensor’s receipt thereof. (b) (i) If, during the performance of the Condemnation Restoration Work or the Casualty Restoration Work required as a result of any Condemnation or Casualty, the Knicks reasonably believe that the substantial completion of such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, will not, absent extraordinary efforts that Licensor does not agree (if not already obligated to take pursuant to this Agreement), be achieved by the applicable Condemnation Outside Date or applicable Casualty Outside Date therefor (as such Condemnation Outside Date or such Casualty Outside Date may have theretofore been postponed pursuant to the provisions of Section 12.01(d) or Section 12.02(d) above, respectively), then the Knicks, by notice given to Licensor and the Estimator, shall have the right (not to be exercised more than once in any six (6) month period) with respect to such Condemnation or such Casualty to request that the Estimator determine the estimated date (the “Revised Estimated Date”) by which such Condemnation Restoration Work or such Casualty Restoration Work, as the case may be, is then reasonably expected to be substantially completed.

Appears in 1 contract

Samples: Arena License Agreement (MSGE Spinco, Inc.)

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!