Information re Deductions. Where the Scheduled Amount is less than the amount claimed in the payment claim, the payment schedule must indicate: 7.7.1 the manner which the Principal has calculated the Scheduled Amount; and 7.7.2 the Principal's reasons for the difference between the Scheduled Amount and the amount of the payment claim; and 7.7.3 where the difference is because the Principal is withholding payment on any basis, the Principal's reasons for withholding payment.
Appears in 2 contracts
Samples: Medium Works Contract, Medium Works Contract
Information re Deductions. Where the Scheduled Amount is less than the amount claimed in the payment claim, the payment schedule must indicate:
7.7.1 the manner in which the Principal has calculated the Scheduled Amount; and
7.7.2 the Principal's ’s reasons for the difference between the Scheduled Amount and the amount of the payment claim; and
7.7.3 where the difference is because the Principal is withholding payment on any basis, the Principal's ’s reasons for withholding payment.
Appears in 2 contracts
Samples: Medium Works Contract, Medium Works Contract
Information re Deductions. Where the Scheduled Amount is less than the amount claimed in the payment claim, the payment schedule must indicate:
7.7.1 the manner which the Principal has calculated the Scheduled Amount; and
7.7.2 the Principal's ’s reasons for the difference between the Scheduled Amount and the amount of the payment claim; and
7.7.3 where the difference is because the Principal is withholding payment on any basis, the Principal's ’s reasons for withholding payment.
Appears in 2 contracts
Samples: Medium Works Contract, Medium Works Contract