Initial Commercial Operation Test. At least thirty (30) days prior to the Expected Initial Delivery Date, Seller shall schedule and complete an Initial Commercial Operation Test for each Generating Unit. Such Initial Commercial Operation Test shall be scheduled and conducted in accordance with Appendix 7. Seller shall use commercially reasonable efforts to undertake such activities in sufficient time to achieve Commercial Operation of each Generating Unit by the Expected Initial Delivery Date and SCE will reasonably cooperate with Seller to meet such deadline. The Initial Commercial Operation Test shall establish the Contract Capacity for purposes of calculating the Monthly Capacity Payment, and Appendix 1.02 and Appendix 9.02 shall be deemed to be amended to reflect the Contract Capacity certified during such test by SCE test personnel.
Appears in 2 contracts
Samples: Resource Adequacy Purchase Agreement, Resource Adequacy Purchase Agreement
Initial Commercial Operation Test. At least thirty (30) days prior to the Expected Initial Delivery Date, Seller shall schedule and complete an Initial Commercial Operation Test for each Generating Storage Unit. Such Initial Commercial Operation Test shall be scheduled and conducted in accordance with Appendix 7. Exhibit C. Seller shall use commercially reasonable efforts to undertake such activities in sufficient time to achieve Commercial Operation of each Generating Storage Unit by the Expected Initial Delivery Date and SCE will reasonably cooperate with Seller to meet such deadline. The Initial Commercial Operation Test shall establish the Contract Capacity for purposes of calculating the Monthly Capacity Payment, and Appendix 1.02 Exhibit D and Appendix 9.02 Exhibit E shall be deemed to be amended to reflect the Contract Capacity certified during such test by SCE test personnel. This test shall be deemed a Seller Initiated Test.
Appears in 1 contract
Samples: Energy Storage Resource Adequacy Purchase and Sale Agreement (Energy Put Option)
Initial Commercial Operation Test. At least thirty (30) days prior to the Expected Initial Delivery Date, Seller shall schedule and complete an Initial Commercial Operation Test for each Generating Storage Unit. Such Initial Commercial Operation Test shall be scheduled and conducted in accordance with Appendix 7. Seller shall use commercially reasonable efforts to undertake such activities in sufficient time to achieve Commercial Operation of each Generating Storage Unit by the Expected Initial Delivery Date and SCE will reasonably cooperate with Seller to meet such deadline. .
(a) The Initial Commercial Operation Test shall establish the Contract Capacity for purposes of calculating the Monthly Capacity Payment, and Appendix 1.02 1.01 and Appendix 9.02 shall be deemed to be amended to reflect the Contract Capacity certified during such test by SCE test personnel.
(b) This test shall be deemed a Seller Initiated Test.
Appears in 1 contract
Samples: Resource Adequacy Purchase Agreement