INITIAL TESTING, STARTUP AND OPERATION. 7.1. Initial testing, startup, and operation shall not commence until all construction required by GRU to establish the point of interconnection is completed and final payments are made, pursuant to Section 3.6 of this Agreement. 7.2. Upon execution of this Agreement, receipt of all required DGR documentation and fees, including the final building and electrical inspection by the local codes enforcement personnel and upon request by Owner/Operator, an authorized representative of GRU shall survey the DGR installation to ensure operational and interconnection requirement compliance. A successful audit and test may result in an immediate interconnection of the DGR. 7.3. In the event that GRU determines, in the exercise of its sole discretion as a result of the above mentioned survey, that the DGR is unacceptable for interconnection, GRU shall provide Owner/Operator written notice of the DGR deficiencies including but not limited to safety and/or reliability risks. Such notice shall include a list of all noted DGR equipment or documentation issues that must be remedied. Owner/Operator shall be solely responsible for correcting all deficiencies and notifying GRU of readiness for another survey and possible interconnection. A failed DGR survey will prevent interconnection until all deficiencies have been remedied.
Appears in 2 contracts
Samples: Interconnection Agreement, Interconnection Agreement
INITIAL TESTING, STARTUP AND OPERATION. 7.1. Initial testing, startup, and operation shall not commence until all construction required by GRU to establish the point of interconnection is completed and final payments are made, pursuant to Section 3.6 of this Agreement.
7.2. Upon execution of this Agreement, receipt of all required DGR documentation and fees, including the final building and electrical inspection by the local codes enforcement personnel and upon request by Owner/Operator, an authorized representative of GRU shall survey the DGR installation to ensure operational and interconnection requirement compliance. A successful audit and test may result in an immediate interconnection of the DGR.
7.3. In the event that GRU determines, in the exercise of its sole discretion as a result of the above mentioned survey, that the DGR is unacceptable for interconnection, GRU shall provide Owner/Operator written notice of the DGR deficiencies including but not limited to safety and/or reliability risks. Such notice shall include a list of all noted DGR equipment or documentation issues that must be remedied. Owner/Operator shall be solely responsible for correcting all deficiencies and 3 GRU Energy Delivery Service Guide notifying GRU of readiness for another survey and possible interconnection. A failed DGR survey will prevent interconnection until all deficiencies have been remedied.
Appears in 2 contracts
Samples: Interconnection Agreement, Interconnection Agreement