Common use of Inspection and On-Going Compliance Clause in Contracts

Inspection and On-Going Compliance. 4.1. All initial physical inspections and inspection of Customer’s documents must be completed by FPL within thirty (30) calendar days of receipt of the Customer’s executed Interconnection Agreement. If the inspection is delayed at the Customer’s request, the Customer shall contact FPL to reschedule an inspection. FPL shall reschedule the inspection within ten (10) business days of the Customer’s request. Physical inspections and inspection of documents must be completed and approved by FPL prior to commencement of service of the Customer-owned renewable generation system.