Interconnection Evaluation Study Procedures. Upon receipt of an executed Interconnection Evaluation Study Agreement, payment of the estimated cost, and all relevant technical data necessary for completing the Interconnection Evaluation Study, the Transmission Provider or ITC, as applicable, will use or cause to be used due diligence to complete the Interconnection Evaluation Study within sixty (60) days after receipt of the executed Interconnection Evaluation Study Agreement, payment of such estimated cost and all such relevant technical data, provided that Generator does not elect to have Phase 1 and Phase 2 performed sequentially as provided in Section 5.4. If Generator fails to provide such payment and/or all such necessary relevant technical data, the Transmission Provider shall notify Generator of such deficiencies within seven (7) days of the receipt of the executed Interconnection Evaluation Study Agreement. Generator shall provide the Transmission Provider with the required payment and/or