INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26, 2015. The completion date for this intermediate contract time is May 25, 2017. The liquidated damages for this intermediate contract time are Two Thousand Dollars ($ 2,000.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Roadway Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26July 8, 20152019. The completion date for this intermediate contract time is May 25September 15, 20172021. The liquidated damages for this intermediate contract time are Two Thousand Dollars ($ 2,000.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for responsiblefor and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Roadway Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26August 28, 20152017. The completion date for this intermediate contract time is May 25October 1, 20172018. The liquidated damages for this intermediate contract time are Two Thousand Dollars ($ 2,000.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Roadway & Structure Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26February 1, 20152016. The completion date for this intermediate contract time is May 25September 30, 20172016. The liquidated damages for this intermediate contract time are Two Thousand Seven Hundred Fifty Dollars ($ 2,000.00750.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Construction Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26June 18, 20152012. The completion date for this intermediate contract time is May 25, 2017. the date which is one hundred and twenty The liquidated damages for this intermediate contract time are Two Thousand Five Hundred Dollars ($ 2,000.00$500.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Construction Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26March 2, 2015. The completion date for this intermediate contract time is May 25September 1, 2017. The liquidated damages for this intermediate contract time are Two Three Thousand Dollars ($ 2,000.003,000.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Roadway & Structure Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26September 25, 20152017. The completion date for this intermediate contract time is May 25November 1, 20172018. The liquidated damages for this intermediate contract time are Two Thousand Seven Hundred Fifty Dollars ($ 2,000.00750.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Roadway & Structure Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26April 2, 20152018. The completion date for this intermediate contract time is May 25December 14, 20172018. The liquidated damages for this intermediate contract time are Two One Thousand Dollars ($ 2,000.001,000.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Contract
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES. (7-1-95) (Rev. 2-21-12) 108 SP1 G13 A Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. The date of availability for this intermediate contract time is October 26, 2015the date of availability for this contract. The completion date for this intermediate contract time is May 25August 1, 20172024. The liquidated damages for this intermediate contract time are Two One Thousand Five Hundred Dollars ($ 2,000.001,500.00) per calendar day. Upon apparent completion of all the work required to be completed by this intermediate date, a final inspection will be held in accordance with Article 105-17 and upon acceptance, the Department will assume responsibility for the maintenance of all work except Planting, Reforestation and/or Permanent Vegetation Establishment. The Contractor will be responsible for and shall make corrections of all damages to the completed roadway caused by his planting operations, whether occurring prior to or after placing traffic through the project.
Appears in 1 contract
Samples: Contract