Knowledge of Site Conditions. The Subcontractor warrants to Honeywell that it has fully informed itself in relation to the Site and all the conditions that are relevant to the performance of the Works. The Subcontractor agrees that: 1) It is deemed to have verified the Site Conditions and it has No Claim in respect of any failure by the Subcontractor to properly and reasonably inspect the Site and to make all reasonable enquiries with respect to and in connection with the Site; 2) Subcontractor assumes and bears the risk of all adverse Site Conditions which occur or may be discovered during the course of carrying out the Works; 3) Honeywell gives no warranty whatsoever regarding the accuracy or completeness of any of the information in respect of the Site and Site Conditions which Honeywell has provided to the Subcontractor; and 4) It has No Claim arising out of or in connection with the supply or non-supply by Honeywell of any information or documentation relating to: (i) the Site and the Site Conditions; (ii) the areas adjacent to the Site or below the surface of the Site; or (iii) any other matter or thing of whatsoever nature relating to the Site.
Appears in 3 contracts
Samples: Subcontract Agreement, Subcontract Agreement, Subcontract Agreement
Knowledge of Site Conditions. The Subcontractor warrants to Honeywell that it has fully informed itself in relation to the Site and all the conditions that are relevant to the performance of the Works. The Subcontractor agrees that:
1) It is deemed to have verified the Site Conditions and it has No Claim in respect of any failure by the Subcontractor to properly and reasonably inspect the Site and to make all reasonable enquiries with respect to and in connection with the Site;
2) Subcontractor assumes and bears the risk of all adverse Site Conditions which occur or may be discovered during the course of carrying out the Works;
3) Honeywell gives no warranty whatsoever regarding the accuracy or completeness of any of the information in respect of the Site and Site Conditions which Honeywell has provided to the Subcontractor; and
4) It has No Claim arising out of or in connection with the supply or non-supply by Honeywell of any information or documentation relating to: (i) the Site and the Site ConditionsSite; (ii) the areas adjacent to the Site or below the surface of the Site; or (iii) any other matter or thing of whatsoever nature relating to the Site.
Appears in 1 contract
Samples: Subcontract Agreement
Knowledge of Site Conditions. The Subcontractor warrants to Honeywell that it has fully informed itself in relation to the Site and Site Conditions and all the conditions that are relevant to the performance of the Works. The Subcontractor agrees that:
1) It is deemed to have verified the Site Conditions and it has No Claim in respect of any failure by the Subcontractor to properly and reasonably inspect the Site and to make all reasonable enquiries with respect to and in connection with the Site;
2) Subcontractor assumes and bears the risk of all adverse Site Conditions which occur or may be discovered during the course of carrying out the Works;
3) Honeywell gives no warranty whatsoever regarding the accuracy or completeness of any of the information in respect of the Site and Site Conditions which Honeywell has provided to the Subcontractor; and
4) It has No Claim arising out of or in connection with the supply or non-supply by Honeywell of any information or documentation relating to: (i) the Site and the Site Conditions; (ii) the areas adjacent to the Site or below the surface of the Site; or (iii) any other matter or thing of whatsoever nature relating to the Site.
Appears in 1 contract
Samples: Subcontract Agreement