Common use of Liquidated Damage Amounts Clause in Contracts

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 2 contracts

Samples: Construction Agreement, Construction Agreement

AutoNDA by SimpleDocs

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 2 contracts

Samples: Construction Contract, Construction Agreement

Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. 4.1.2. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 2 contracts

Samples: Construction Agreement, Construction Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five Hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Contract Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty Five Hundred dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Services Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two five hundred-fifty dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two five hundred-fifty dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty hundred dollars ($250.00200.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty hundred dollars ($250.00200.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Services Agreement

Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Thousand Dollars ($250.002000) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. 4.1.2. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Thousand Dollars ($250.002000) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Agreement

Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Hundred Fifty Dollars ($250.00250) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. 4.1.2. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Two Hundred Fifty Dollars ($250.00250) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty one thousand dollars ($250.001,000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty One Thousand Hundred dollars ($250.001,000.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty Five Hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty Five Hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Services Agreement

AutoNDA by SimpleDocs

Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. 4.1.2. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars One Thousand Dollars ($250.001000.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. achieved. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved. Measures of liquidated damages shall apply cumulatively. Limitations and stipulations regarding liquidated damages are set forth in Document 00 7200 (General Conditions).

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor Design-Build Entity shall pay Owner two hundredone thousand dollars ($1,000.00) for each Day that expires after the time specified herein for Design-fifty Build Entity to achieve Substantial Completion of the entire Work, until achieved. B. As liquidated damages for delay Design-Build Entity shall pay Owner Two-Hundred and Fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundredDesign-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor Build Entity to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five hundred dollars ($250.00500.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty five thousand dollars ($250.005,000.00) for each Day day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty one thousand five hundred dollars ($250.001,500.00) for each Day say that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty One thousand nine hundred dollars ($250.00) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌ B. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars ($250.001,900.00) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Contract

Liquidated Damage Amounts. A. 4.1.1. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Five Hundred Dollars ($250.00500) for each Day that expires after the time specified herein for Contractor to achieve Substantial Completion of the entire Work, until achieved.‌achieved. B. 4.1.2. As liquidated damages for delay Contractor shall pay Owner two hundred-fifty dollars Five Hundred Dollars ($250.00500) for each Day that expires after the time specified herein for Contractor to achieve Final Completion of the entire Work, until achieved.

Appears in 1 contract

Samples: Construction Agreement