Liquidated Damages; Extension of Time. In accordance with Government Code Section 53069.85, Contractor agrees to forfeit and pay to County the sum of Five Hundred Dollars ($500), per day for each calendar day work is delayed beyond the time allowed, and such sum shall be deducted from any payments due to or to become due to Contractor. Contractor will be granted an extension of time and will not be assessed liquidated damages for unforeseeable delays beyond the control of and without the fault or negligence of the Contractor including delays caused by County.
Appears in 6 contracts
Samples: Contract for Structured Cabling and Installation Services, Contract for Structured Cabling and Installation Services, Contract for Structured Cabling and Installation Services