Common use of Liquidated Damages for Delay in achieving COD of Project Clause in Contracts

Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s / Project’s Scheduled COD as extended under Articles 4.4.1 and 4.4.2, then the TSP shall pay to the Long Term Transmission Customer(s), as communicated by the Lead Long Term Transmission Customer, in proportion to their Allocated Project Capacity as on the date seven (7) days prior to the Bid Deadline, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Project, as liquidated damages for such delay and not as penalty, without prejudice to Long Term Transmission Customers’ any rights under the Agreement.

Appears in 4 contracts

Samples: Transmission Service Agreement, Transmission Service Agreement, Draft Transmission Service Agreement

AutoNDA by SimpleDocs

Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s Element‟s / Project’s Project‟s Scheduled COD as extended under Articles 4.4.1 and 4.4.2, then the TSP shall pay to the Long Term Transmission Customer(s), as communicated by the Lead Long Term Transmission Customer, in proportion to their Allocated Project Capacity as on the date seven (7) days prior to the Bid Deadline, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Project, as liquidated damages for such delay and not as penalty, without prejudice to Long Term Transmission Customers’ Customers‟ any rights under the Agreement.

Appears in 4 contracts

Samples: Transmission Service Agreement, Transmission Service Agreement, Transmission Service Agreement

AutoNDA by SimpleDocs

Liquidated Damages for Delay in achieving COD of Project. 6.4.1 If the TSP fails to achieve COD of any Element of the Project or the Project, by the Element’s / Project’s Element‟s/ Project‟s Scheduled COD as extended under Articles 4.4.1 and 4.4.2, then the TSP shall pay to the Long Term Transmission Customer(s), as communicated by the Lead Long Term Transmission Customer, in proportion to their Allocated Project Capacity as on the date seven (7) days prior to the Bid Deadline, a sum equivalent to 3.33% of Monthly Transmission Charges applicable for the Element of the Project [in case where no Elements have been defined, to be on the Project as a whole] / whole]/ Project, for each day of delay up to sixty (60) days of delay and beyond that time limit, at the rate of five percent (5%) of the Monthly Transmission Charges applicable to such Element / Element/ Project, as liquidated damages for such delay and not as penalty, without prejudice to Long Term Transmission Customers’ Customers‟ any rights under the Agreement.

Appears in 1 contract

Samples: Transmission Service Agreement