Common use of Liquidated Damages Respecting Delays Clause in Contracts

Liquidated Damages Respecting Delays. 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows: (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline; (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; and (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

Liquidated Damages Respecting Delays. ‌‌ 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows: (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline; (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; and (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damages Respecting Delays. 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows: (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline; (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; andand‌ (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.Conditions.‌

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damages Respecting Delays. 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows:follows:‌ (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; and (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damages Respecting Delays. 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows:follows:‌ (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; and (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.

Appears in 1 contract

Samples: Design Build Agreement

AutoNDA by SimpleDocs

Liquidated Damages Respecting Delays. 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows: (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline;Deadline;‌ (b) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (c) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (d) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline; (e) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (f) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; andand‌ (g) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance. 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.Conditions.‌

Appears in 1 contract

Samples: Design Build Agreement

Liquidated Damages Respecting Delays. ‌‌ 7.2.1 The amounts of any liquidated damages for which DB Contractor may be liable pursuant to Section 8.7.1 of the General Conditions shall be as follows: (a) $10,000 for each day after the Old Bee Cave Road Offsite Detention Area Completion Deadline and through the earlier of (a) the date of Old Bee Cave Road Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (b) $10,000 for each day after the SH 71 Offsite Detention Area Completion Deadline and through the earlier of (a) the date of SH 71 Offsite Detention Area Completion, and (b) the Substantial Completion Deadline; (c) $36,000 for each day after the US 290 Westbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound East Segment Completion, and (b) the Substantial Completion Deadline; (cd) $33,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound East Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound East Segment Completion, and (b) the Substantial Completion Deadline; (de) $11,000 for each day after the US 290 Westbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Westbound West Segment Completion, and (b) the Substantial Completion Deadline; (ef) $13,500 for each day after the US 000 Xxxxxxxxx Xxxx 290 Eastbound West Segment Completion Deadline and through the earlier of (a) the date of US 290 Eastbound West Segment Completion, and (b) the Substantial Completion Deadline; (fg) $114,000 for each day after the Substantial Completion Deadline and through the date of Substantial Completion, but not to exceed 365 days; and (gh) $7,600 per day for each day after the Final Acceptance Deadline and through the date of Final Acceptance.Acceptance.‌ 7.2.2 DB Contractor acknowledges that the liquidated damages described in this Section 7.2 are reasonable in order to compensate TxDOT for damages it will incur as a result of late completion of the Project or portions thereof as set forth in this Section 7.2 and Section 8.7 of the General Conditions.Conditions.‌