Milestone Extensions. Each Milestone (and each subsequent Milestone, including the Expected Commercial Operation Date and the Guaranteed Commercial Operation Date, as applicable) shall be extended to the extent reasonably required following an event of Force Majeure or Buyer’s breach of this Agreement, in each case, that impacts the achievement of such Milestone.
Appears in 2 contracts
Milestone Extensions. Each Milestone (and each subsequent Milestone, including the Expected Commercial Operation Date and the Guaranteed Outside Commercial Operation Date, as applicable) shall be extended to the extent reasonably required following an event of Force Majeure or BuyerCVEC’s breach of this Agreement, in each case, that impacts the achievement of such Milestone.
Appears in 2 contracts
Samples: Solar Power Purchase and Development Agreement, Solar Power Purchase and Development Agreement