Minimising Disruption. 13.1 If it appears likely to the Contractor that any planned works or activities to be carried out by the Contractor under this Contract will necessitate interruption to or restriction of the System and/or require access to any Purchaser Property, then the Contractor shall notify Purchaser not less than fourteen (14) days prior to such planned works or activities. 13.2 In the event of any unplanned works or activities to be carried out by the Contractor as a result of a System Fault or otherwise, then the Contractor shall notify Purchaser as soon as possible of the nature of such works or activities and the likely disruption or restriction of the System. 13.3 The Contractor shall perform the Services:
Appears in 3 contracts
Samples: Supply of Goods and Services Agreement, Supply of Goods and Services Agreement, Supply of Goods and Services Agreement
Minimising Disruption. 13.1 12.1 If it appears likely to the Contractor that any planned works or activities to be carried out by the Contractor under this Contract will necessitate interruption to or restriction of the System Managed Service and/or require access to any Purchaser Property, then the Contractor shall notify Purchaser not less than fourteen (14) days prior to such planned works or activities.
13.2 12.2 In the event of any unplanned works or activities to be carried out by the Contractor as a result of a System Managed Service Fault or otherwise, then the Contractor shall notify Purchaser as soon as possible of the nature of such works or activities and the likely disruption or restriction of the SystemManaged Service.
13.3 12.3 The Contractor shall perform the Services:
Appears in 1 contract