Mobilization Phase Plan and Budget Sample Clauses
Mobilization Phase Plan and Budget. (a) Within 60 days after the date of execution of this Agreement, Operator shall prepare and submit to the Management Committee for the Management Committee’s review and approval a plan (the “Mobilization Phase Plan”) and budget (the “Mobilization Phase Budget”) for the Mobilization Phase.
(b) The Mobilization Phase Budget shall be itemized on a monthly basis and incorporate all proposed Budgeted Expenses anticipated: (i) to perform the Mobilization Phase Services; (ii) to prepare the Agreed Procedures more fully described in Schedule 1; (iii) to complete the transition from the Mobilization Phase to the Commercial Operation Phase; (iv) to assist Owner and the Construction Manager with the commissioning, testing, start-up and operation of all equipment at the Project; and (v) to perform all other Mobilization Phase Services.
(c) The Mobilization Phase Plan shall set forth in a monthly timetable a program of performance for the Mobilization Phase Services.
(d) Within 30 days of receiving the proposed Mobilization Phase Plan and Mobilization Phase Budget, the Management Committee shall provide written comments to Operator and request any additions, changes or modifications to such Plan and Budget. The Management Committee and Operator shall, not less than 10 days following Operator’s receipt of the Management Committee’s comments, meet to discuss and resolve the terms of such Plan and Budget and the Management Committee’s requested changes thereto.