Modification Costs. Unless otherwise required by Applicable Laws and Regulations or this Appendix 2 and, with respect to a Transmission Interconnection Customer, subject to the terms of Section 236.2 of the Tariff: (a) Interconnection Customer shall not be responsible for the costs of any additions, modifications, or replacements that the Interconnected Transmission Owner in its discretion or at the direction of Transmission Provider makes to the Interconnection Facilities or the Transmission System in order to facilitate the interconnection of a third party to the Interconnection Facilities or the Transmission System, or to provide transmission service under the Tariff to a third party. (b) Interconnection Customer shall be responsible for the costs of any additions, modifications, or replacements to the Interconnection Facilities or the Transmission System that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements made by Interconnection Customer to the Customer Facility or to the Customer Interconnection Facilities. (c) Interconnection Customer shall be responsible for the costs of any additions, modifications, or replacements to the Customer Interconnection Facilities or the Customer Facility that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements that Transmission Provider or the Interconnected Transmission Owner makes to the Transmission System or to the Transmission Owner Interconnection Facilities, but only to the extent that Transmission Provider’s or the Interconnected Transmission Owner’s changes to the Transmission System or the Transmission Owner Interconnection Facilities are made pursuant to Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards.
Appears in 81 contracts
Samples: Interconnection Service Agreement, Interconnection Service Agreement, Interconnection Service Agreement
Modification Costs. Unless otherwise required by Applicable Laws and Regulations or this Appendix 2 and, with respect to a Transmission Interconnection CustomerProject Developer, subject to the terms of Section 236.2 of the TariffGIP, section [to be provided]:
(a) Interconnection Customer Project Developer shall not be responsible for the costs of any additions, modifications, or replacements that the Interconnected Transmission Owner in its discretion or at the direction of Transmission Provider makes to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System in order to facilitate the interconnection of a third party to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System, or to provide transmission service under the Tariff to a third party.
(b) Interconnection Customer Project Developer shall be responsible for the costs of any additions, modifications, or replacements to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements made by Interconnection Customer Project Developer to the Customer Generating Facility or Merchant Transmission Facility or to the Customer Project Developer Interconnection Facilities.
(c) Interconnection Customer Project Developer shall be responsible for the costs of any additions, modifications, or replacements to the Customer Project Developer Interconnection Facilities or the Customer Generating Facility or Merchant Transmission Facility that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements that Transmission Provider or the Interconnected Transmission Owner makes to the Transmission System or to the Transmission Owner Interconnection FacilitiesFacilities and Transmission Owner Upgrades, but only to the extent that Transmission Provider’s or the Interconnected Transmission Owner’s changes to the Transmission System or the Transmission Owner Interconnection Facilities and Transmission Owner Upgrades are made pursuant to Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards.
Appears in 9 contracts
Samples: Execution Deadlines, Execution Deadlines, Execution Deadlines
Modification Costs. Unless otherwise required by Applicable Laws and Regulations or this Appendix 2 and, with respect to a Transmission Interconnection Customer, subject to the terms of Section 236.2 of the Tariff:
(a) Interconnection Customer shall not be responsible for the costs of any additions, modifications, or replacements that the Interconnected Transmission Owner in its discretion or at the direction of Transmission Provider makes to the Interconnection Facilities or the Transmission System in order to facilitate the interconnection of a third party to the Interconnection Facilities or the Transmission System, or to provide transmission service under the Tariff to a third party.
(b) Interconnection Customer shall be responsible for the costs of any additions, modifications, or replacements to the Interconnection Facilities or the Transmission System that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements made by Interconnection Customer to the Customer Facility or to the Customer Interconnection Facilities.
(c) Interconnection Customer shall be responsible for the costs of any additions, modifications, or replacements to the Customer Interconnection Facilities or the Customer Facility that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements that Transmission Provider or the Interconnected Transmission Owner makes to the Transmission System or to the Transmission Owner Interconnection Facilities, but only to the extent that Transmission Provider’s or the Interconnected Transmission Owner’s changes to the Transmission System or the Transmission Owner Interconnection Facilities are made pursuant to Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards.Transmission
Appears in 2 contracts
Samples: Interconnection Service Agreement, Interconnection Service Agreement
Modification Costs. Unless Subject to Article 9.9, Interconnection Customer shall be directly assigned and must pay for the costs of any additions, modifications, or replacements to Transmission Provider's Interconnection Facilities that are necessary to accommodate modifications made by Interconnection Customer to Interconnection Customer’s Interconnection Facilities and/or Generating Facility or are otherwise required by necessary to maintain or upgrade Transmission Provider's Interconnection Facilities consistent with Applicable Laws and Regulations or this Appendix 2 andRegulations, with respect Applicable Reliability Standards, Transmission Provider’s Technical Standards, and/or Good Utility Practice. In addition, Interconnection Customer must pay for the costs of any Network Upgrades and/or Distribution Upgrades that are necessary to a Transmission accommodate modifications made by Interconnection Customer to Interconnection Customer’s Interconnection Facilities and/or Generating Facility. Subject to Section 4 of Transmission Provider’s GIP and Article 9.9 of this GIA, subject to the terms of Section 236.2 of the Tariff:
(a) Interconnection Customer shall not be responsible directly assigned for the costs of any additions, modifications, or replacements that the Interconnected Transmission Owner in its discretion or at the direction of Transmission Provider makes to the Transmission Provider’s Interconnection Facilities Facilities, Transmission System, or the Transmission Distribution System in order solely to facilitate the interconnection of a third party to the Transmission Provider’s Interconnection Facilities Facilities, Transmission System, or the Transmission Distribution System, or to provide transmission service under the Tariff to a third party.
(b) party under Transmission Provider’s Tariff. Interconnection Customer shall be responsible provide security to Transmission Provider for the estimated costs of any the additions, modifications, or replacements to the Interconnection Facilities or the Transmission System that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements made by Interconnection Customer to the Customer Facility or to the Customer Provider's Interconnection Facilities.
(c) Interconnection Customer shall be responsible , Network Upgrades and/or Distribution Upgrades in accordance with Article 11 of this GIA and make payments for the costs design, procurement and construction of any such additions, modifications, or replacements to the Customer Interconnection Facilities or the Customer Facility that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements that Transmission Provider or the Interconnected Transmission Owner makes to the Transmission System or to the Transmission Owner Provider's Interconnection Facilities, but only to the extent that Transmission Provider’s or the Interconnected Transmission Owner’s changes to the Transmission System or the Transmission Owner Interconnection Facilities are made pursuant to Good Utility Practice Network Upgrades and/or to maintain compliance Distribution Upgrades in accordance with Applicable Laws a construction and Regulations or Applicable Standards.payment schedule agreed to
Appears in 1 contract
Samples: Generator Interconnection Agreement
Modification Costs. Unless otherwise required by Applicable Laws and Regulations or this Appendix 2 and, with respect to a Transmission Interconnection CustomerProject Developer, subject to the terms of Section 236.2 of the TariffGIP,:
(a) Interconnection Customer Project Developer shall not be responsible for the costs of any additions, modifications, or replacements that the Interconnected Transmission Owner in its discretion or at the direction of Transmission Provider makes to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System in order to facilitate the interconnection of a third party to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System, or to provide transmission service under the Tariff to a third party.
(b) Interconnection Customer Project Developer shall be responsible for the costs of any additions, modifications, or replacements to the Interconnection Facilities and Transmission Owner Upgrades or the Transmission System that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements made by Interconnection Customer Project Developer to the Customer Generating Facility or Merchant Transmission Facility or to the Customer Project Developer Interconnection Facilities.
(c) Interconnection Customer Project Developer shall be responsible for the costs of any additions, modifications, or replacements to the Customer Project Developer Interconnection Facilities or the Customer Generating Facility or Merchant Transmission Facility that are required, in accord with Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards, in order to accommodate additions, modifications, or replacements that Transmission Provider or the Interconnected Transmission Owner makes to the Transmission System or to the Transmission Owner Interconnection FacilitiesFacilities and Transmission Owner Upgrades, but only to the extent that Transmission Provider’s or the Interconnected Transmission Owner’s changes to the Transmission System or the Transmission Owner Interconnection Facilities and Transmission Owner Upgrades are made pursuant to Good Utility Practice and/or to maintain compliance with Applicable Laws and Regulations or Applicable Standards.
Appears in 1 contract