Modification to the Facility. 11.1 The Prosumer shall not make, without CEB’s prior consent, any modification or addition to the Facility, which includes modification of connection assets, except where the modification will not increase the maximum electrical output of the Facility. In such case, the Prosumer shall give the CEB no less than 15 working days’ prior notice before the modification will be made. 11.2 Where the modification will increase the maximum electrical output of the Facility, the Prosumer shall submit a new application for connection. CEB reserves the right to accept or reject the application. 11.3 If the application is admissible, CEB shall process the application for connection in accordance with Section 5 of this Agreement, the prevailing or other relevant Schemes, if any, and other conditions that will be in force at the time of the new application. 11.4 The Prosumer shall not commence any modification until all necessary procedures have been duly completed. 11.5 In the event the Prosumer applies for relocation of the Facility to another location during the lifetime of this Agreement, the request may be entertained subject to CEB’s approval. 11.6 In respect of the relocation of the Facility, the Prosumer shall fulfil all required procedures and shall sign an addendum to the Connection Agreement, which will last only for the remaining number of years.
Appears in 2 contracts
Samples: Connection Agreement, Connection Agreement
Modification to the Facility. 11.1 The Prosumer Facility Owner shall not make, without CEB’s prior consent, any modification or addition to the Facility, which includes modification of connection assets, except where the modification will not increase the maximum electrical output of the Facility. In such case, the Prosumer Facility Owner shall give the CEB no less than 15 working days’ prior notice before the modification will be made.
11.2 Where the modification will increase the maximum electrical output of the Facility, the Prosumer Facility Owner shall submit a new application for connection. CEB reserves the right to accept or reject the application.
11.3 If the application is admissible, CEB shall process the application for connection in accordance with Section 5 of this Agreement, the prevailing or other relevant Schemes, if any, and other conditions that will be in force at the time of the new application.
11.4 The Prosumer Facility Owner shall not commence any modification until all necessary procedures have been duly completed.
11.5 In the event the Prosumer Facility Owner applies for relocation of the Facility to another location during the lifetime of this Agreement, the request may be entertained subject to CEB’s approvala network impact assessment or survey in the area where the Facility will be relocated.
11.6 In respect of the relocation of the Facility, the Prosumer Facility Owner shall fulfil all required procedures and shall sign an addendum to the Connection Interconnection Agreement, which will last only for the remaining number of years.
Appears in 2 contracts
Samples: Interconnection Agreement, Interconnection Agreement
Modification to the Facility. 11.1 The Prosumer Facility Owner shall not make, without CEB’s prior consent, any modification or addition to the Facility, which includes modification of connection assets, except where the modification will not increase the maximum electrical output of the Facility. In such case, the Prosumer Facility Owner shall give the CEB no less than 15 working days’ prior notice before the modification will be made.
11.2 Where the modification will increase the maximum electrical output of the Facility, the Prosumer Facility Owner shall submit a new application for connection. CEB reserves the right to accept or reject the application.
11.3 If the application is admissible, CEB shall process the application for connection in accordance with Section 5 of this Agreement, the prevailing or other relevant Schemes, if any, and other conditions that will be in force at the time of the new application.
11.4 The Prosumer Facility Owner shall not commence any modification until all necessary procedures have been duly completed.
11.5 In the event the Prosumer Facility Owner applies for relocation of the Facility to another location during the lifetime of this Agreement, the request may be entertained subject to CEB’s approvala network impact assessment or survey in the area where the Facility will be relocated.
11.6 In respect of the relocation of the Facility, the Prosumer Facility Owner shall fulfil all required procedures and shall sign an addendum to the Connection Agreement, which will last only for the remaining number of years.
Appears in 1 contract
Samples: Connection Agreement