Common use of Modifications to the Facility Clause in Contracts

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days notice prior to the date on which the modification will be completed. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 10 contracts

Samples: Connection Agreement, Connection Agreement, Connection Agreement

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days notice prior to the date on which the modification will be completed. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 3 contracts

Samples: Connection Agreement, Connection Agreement, Connection Agreement

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days days’ notice prior to the date on which the modification will be completed. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 2 contracts

Samples: Connection Agreement, Connection Agreement

Modifications to the Facility. 8.1 8.1. The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days notice prior to the date on which the modification will be completed. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 1 contract

Samples: Connection Agreement

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days notice prior to the date on which the modification will be completedmade. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 1 contract

Samples: Connection Agreement

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days notice prior to the date on which the modification will be completed. Where the modification will increase the maximum electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 1 contract

Samples: Connection Agreement

Modifications to the Facility. 8.1 The Customer shall not modify its connection assets or the Facility except in accordance with this section. Where the modification will not increase the maximum generation electrical output of the Facility, the Customer shall give the Distributor no less than 15 working days days’ notice prior to the date on which the modification will be completed. Where the modification will increase the maximum Customer electrical output of the Facility, the Customer shall submit a new application for connection to the Distributor. The Distributor who shall process that application for connection in accordance with the Code. The Customer shall not commence such modification until that process has been completed.

Appears in 1 contract

Samples: Connection Agreement