Nature and extent of relief for Force Majeure. Force Majeure relief under this Clause 17: (a) extinguishes: (i) the obligation of the Affected Party to perform a Relevant Obligation to the extent that it is prevented from doing so by reason of the Relevant Force Majeure Event; and (ii) the obligation of the Affected Party to indemnify the other party under Clause 8.2 in respect of Relevant Losses sustained as a result of the failure of the Affected Party to perform a Relevant Obligation; but (b) is not available in respect of: (i) any obligation to pay money under Schedule 4, Schedule 7 and Schedule 8; or (ii) any other obligation to do or refrain from doing any other thing provided for in this Contract; and (c) is only available in relation to a failure to perform an obligation under the CCOS Network Code to the extent (including as to time and conditions) that the CCOS Network Code so provides.
Appears in 6 contracts
Samples: Track Access Contract, Track Access Contract, Track Access Contract
Nature and extent of relief for Force Majeure. Force Majeure relief under this Clause 17:
(a) extinguishes:
(i) the obligation of the Affected Party to perform a Relevant Obligation to the extent that it is prevented from doing so by reason of the Relevant Force Majeure Event; and
(ii) the obligation of the Affected Party to indemnify the other party under Clause 8.2 in respect of Relevant Losses sustained as a result of the failure of the Affected Party to perform a Relevant Obligation; but
(b) is not available in respect of:
(i) any obligation to pay money under Schedule 4, Schedule 7 and Schedule 8; or
(ii) any other obligation to do or refrain from doing any other thing provided for in this Contract; and
(c) is only available in relation to a failure to perform an obligation under the CCOS Network Code to the extent (including as to time and conditions) that the CCOS Network Code so provides.
Appears in 3 contracts
Samples: Track Access Contract, Track Access Contract, Track Access Contract
Nature and extent of relief for Force Majeure. Force Majeure relief under this Clause 17:
(a) extinguishes:
(i) the obligation of the Affected Party to perform a Relevant Obligation to the extent that it is prevented from doing so by reason of the Relevant Force Majeure Event; and
(ii) the obligation of the Affected Party to indemnify the other party under Clause 8.2 in respect of Relevant Losses sustained as a result of the failure of the Affected Party to perform a Relevant Obligation; but
(b) is not available in respect of:
(i) any obligation to pay money under Schedule 4, Schedule 7 and Schedule 8; or
(ii) any other obligation to do or refrain from doing any other thing provided for in this Contractcontract; and
(c) is only available in relation to a failure to perform an obligation under the CCOS Network Code to the extent (including as to time and conditions) that the CCOS Network Code so provides.
Appears in 1 contract
Samples: Track Access Contract