Common use of No Effect on Obligation to Pay Delay Liquidated Damages Clause in Contracts

No Effect on Obligation to Pay Delay Liquidated Damages. Adjustments to the Project Schedule (including the Guaranteed Substantial Completion Date) may occur as a result of any of the events described in this Article VIII. Unless dates for performance are adjusted by an executed Change Order, the obligation to pay Delay Liquidated Damages on the Guaranteed Substantial Completion Date shall not be affected.

Appears in 3 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement

AutoNDA by SimpleDocs

No Effect on Obligation to Pay Delay Liquidated Damages. Adjustments to the Project Schedule (including the Guaranteed Substantial Completion Date) may occur as a result of any of the events described in this Article VIII. Unless dates for performance are adjusted by an executed Change Order, the obligation to pay Delay Liquidated Damages on the Guaranteed Substantial Completion Date shall not be affected.affected.β€Œ

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement