No Price Adjustment. When the ratio SI/ SB falls within the range of 0.95 to 1.05, no price adjustment will be made for applicable steel material having an invoice date that falls within the month for which the SI index price was posted.
Appears in 8 contracts
Samples: Highway Construction Contract, Highway Construction Contract, Highway Construction Contract
No Price Adjustment. When the ratio SI/ SI/SB falls within the range of 0.95 to 1.05, no price adjustment will be made for applicable steel material having an invoice date that falls within the month for which the SI index price was posted.
Appears in 1 contract
Samples: Construction Contract