Nonconformity Records. Design-Builder shall maintain records of:
(a) each Nonconformity, traceable to processes, actual parts, components, locations, drawings and data sheets as appropriate;
(b) the date of the occurrence of the Nonconformity;
(c) the reference numbers of all Nonconformity Reports;
(d) a description of all Nonconformity Reports;
(e) the proposed disposition of each Nonconformity;
(f) the date and time at which Nonconformities were identified or discovered;
(g) the date and time at which Nonconformities were entered into the Nonconformity Tracking System (‘opened date’);
(h) the due date for the preparation of the Proposed Plan and the Final Plan, and the due date for rectifying the Nonconformity;
(i) the date and time at which a Nonconformity specified in a Nonconformity Report was rectified (‘closed date’);
(j) identification of the Nonconformity as a Process NCR or Product NCR;
(k) the date the Final Plan was completed;
(l) the date the Final Plan was submitted to City;
(m) the date the Final Plan was Accepted by the City, and
(n) the priority rating of the NCR, which will be categorized as either:
(i) “Important” or
(ii) “Requires Immediate Action”.
Nonconformity Records. Project Co shall maintain records of:
(a) each Nonconformity, traceable to processes, actual parts, components, locations, drawings and data sheets as appropriate;
(b) the reference numbers of all Nonconformity Reports;
(c) a description of all Nonconformity Reports;
(d) the proposed disposition by Project Co to rectify or correct each Nonconformity;
(e) the date and time at which Nonconformities were identified or discovered;
(f) the date and time at which Nonconformities were entered into the Nonconformity Tracking System (‘opened date’);
(g) the due date for preparation of the Proposed Plan and the due date for rectifying the Nonconformity; and
(h) the date and time at which a Nonconformity specified in a Nonconformity Report was rectified (‘closed date’).