Operating Test Period. Upon receipt of written notice from the Contractor that the Work is ready to be placed into service for the operating test period, the Engineer will, within a reasonable time, inspect the Work. Prior to initiating the operating test, Work required by the Contract Documents must be in place and operable as determined by the Engineer, which includes, but is not limited to the following:
Appears in 9 contracts
Samples: Macon Water Authority, Macon Water Authority, Contract Agreement
Operating Test Period. Upon receipt of written notice from the Contractor that the Work is ready to be placed into service for the operating test period, the Engineer will, within a reasonable time, inspect the Work. Prior to initiating the operating test, Work required by the General Conditions Contract Documents must be in place and operable as determined by the Engineer, which includes, but is not limited to the following:
Appears in 1 contract
Samples: Contract Agreement