Other Additional Proposed Subcontractors and Sub-subcontractors. For any Subcontractor not covered by Sections 2.4A or 2.4B, Contractor shall, within thirty (30) Days prior to the selection of any such Subcontractor, notify Owner in writing of the selection of such Subcontractor and inform Owner generally what portion of the Work such Subcontractor is performing.
Appears in 2 contracts
Samples: Lump Sum Turnkey Agreement (Mirant Corp), Lump Sum Turnkey Agreement (Mirant Corp)
Other Additional Proposed Subcontractors and Sub-subcontractors. For any Subcontractor not covered by Sections 2.4A or 2.4BSection 2.4.1, Contractor shall, within thirty fifteen (3015) Days prior to the selection of any such Subcontractor, notify Owner in writing of the selection of such Subcontractor and inform Owner generally what portion of the Work such Subcontractor is performingperforming at the Site.
Appears in 2 contracts
Samples: Turnkey Agreement (Global Clean Energy Holdings, Inc.), Turnkey Agreement (Global Clean Energy Holdings, Inc.)
Other Additional Proposed Subcontractors and Sub-subcontractors. For any Subcontractor or Sub-subcontractor performing Work on the Site and not otherwise covered by Sections 2.4A or 2.4B, Contractor shall, within thirty fourteen (3014) Days prior to the selection after execution of any a Subcontract with such SubcontractorSubcontractor or Sub-subcontractor, notify Owner in writing of the selection of such Subcontractor or Sub-subcontractor and inform Owner generally what portion of the Work such Subcontractor or Sub-subcontractor is performing.
Appears in 2 contracts
Samples: Fixed Price Turnkey Agreement (NextDecade Corp.), Fixed Price Turnkey Agreement (NextDecade Corp.)
Other Additional Proposed Subcontractors and Sub-subcontractors. For any Subcontractor or Sub-subcontractor not covered by Sections 2.4A or 2.4B, Contractor shall, within thirty fifteen (3015) Days prior to the selection of any such SubcontractorSubcontractor or Sub-subcontractor, notify Owner in writing of the selection of such Subcontractor or Sub-subcontractor and inform Owner generally what portion of the Work such Subcontractor or Sub-subcontractor is performing.
Appears in 2 contracts
Samples: Construction Agreement (Cheniere Corpus Christi Holdings, LLC), Construction Agreement (Cheniere Corpus Christi Holdings, LLC)
Other Additional Proposed Subcontractors and Sub-subcontractors. For any Subcontractor or Sub-subcontractor performing Work on Site and not otherwise covered by Sections 2.4A or 2.4B, Contractor shall, within thirty fourteen (3014) Days prior to the selection after execution of any a Subcontract with such SubcontractorSubcontractor or Sub-subcontractor, notify Owner in writing of the selection of such Subcontractor or Sub-subcontractor and inform Owner generally what portion of the Work such Subcontractor or Sub-subcontractor is performing.
Appears in 1 contract