Owner Coordinated Document Review Process Sample Clauses
Owner Coordinated Document Review Process. A/E agrees to timely deliver the “Owner Coordinated Document Review Process” as follows.
2.1.2.1. During the design phase of the Project, the design schedule shall accommodate a periodic review of the Construction Documents at various milestones, to be coordinated by TFC, at the following milestones and in the sequential order listed: (i) Initial Conceptual Drawings; (ii) Schematic Design; (iii) Design Development; (iv) 65% Construction Documents; (v) 95% Construction Documents; and (vi) 100% Construction Documents.
2.1.2.2. Each review shall include the following steps to comprise a complete review for each milestone listed above.
2.1.2.2.1. The A/E shall have a fixed number of days after TFC’s notice of authorization to A/E to proceed with the next phase of design. The fixed number of days for development of each phase of design is as follows:
(i) Initial Conceptual Drawings, [xxx] (x) calendar days; (ii) Schematic Design, [xxx] (x) calendar days; (iii) Design Development, [xxx] (x) calendar days; (iv) 65% Construction Documents, [xxx] (x) calendar days; (v) 95% Construction Documents, [xxx] (x) calendar days; and (vi) 100% Construction Documents, [xxx] (x) calendar days. The last day of each design phase duration or the first weekday thereafter is the A/E deadline for submitting the design phase deliverables for review.
2.1.2.2.2. TFC, A/E and CMR shall meet to review the milestone submittal, five (5) calendar days or the first weekday thereafter following the A/E deadline.
2.1.2.2.3. The formal review comments and deadline is the date occurring five (5) calendar days or the first weekday thereafter following the review meeting upon which TFC shall prepare and deliver TFC comments to A/E and CMR; and CMR shall prepare and deliver CMR comments to TFC and A/E.
2.1.2.2.4. The A/E reply and deadline is the date occurring five (5) calendar days or the first weekday thereafter following A/E’s receipt of TFC and CMR formal review comments upon which A/E shall provide written evidence that, in TFC’s sole discretion, resolves all TFC and CMR formal comments.
2.1.2.2.5. The A/E’s and/or CMR’s Cost Estimate (as applicable to the A/E’s scope of work) and deadline is the date occurring five (5) calendar days or the first weekday thereafter following delivery of formal review comments to A/E upon which CMR and/or A/E shall prepare and deliver to TFC Cost Estimates in increasing detail and refinement updated through the review of the 100% Construction Documents. Cost ...
Owner Coordinated Document Review Process. A/E agrees to timely deliver the “Owner Coordinated Document Review Process” as follows:
2.1.3.1. During the Project, the design schedule shall accommodate a periodic review of the Master Plan and OPR documents at various milestones, to be coordinated by TFC.
2.1.3.2. TFC and A/E shall meet to review the milestone submittals, five (5) calendar days or the first weekday thereafter following the A/E deadline.
2.1.3.3. The formal review comments and deadline is the date occurring five
Owner Coordinated Document Review Process. BECxA agrees to timely deliver the Owner Coordinated Document Review Process, as follows.
2.1.2.1. During the design phase of each Package, the design schedule shall accommodate a periodic review of the AOR’s and EOR’s design and construction documentation at various milestones, to be coordinated by TFC. The following milestones in the sequential order are: (i) 100% DD (ii) 65% Construction Documents (iii) 95% Construction Documents; and (iv) 100% Construction Documents. BECxA to participate in Design Review conferences and Pre- Construction meetings, provide comments as they relate to building envelope commissioning and update commissioning plans and specifications.
2.1.2.2. Each review shall include the following steps to comprise a complete review for each milestone listed above.
2.1.2.2.1. Five business day review of the AOR/EOR’s document submittal.
2.1.2.2.2. TFC, CMA, Master A/E, AOR/EOR, BECxA and CMR shall meet to review all milestone submittals, as described in the PMP.
2.1.2.2.3. Provide comments and commissioning plan updates at the agreed upon milestone submission schedule as described in the PMP.