Owner May Suspend Work. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) consecutive days by notice in writing to Contractor and Architect which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreement.
Appears in 14 contracts
Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services
Owner May Suspend Work. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than ninety (90) consecutive days by notice in writing to Contractor and Architect DESIGN/BUILDER which will fix the date on which Work will be resumed. Contractor DESIGN/BUILDER shall resume the Work on the date so fixed. Contractor shall DESIGN/BUILDER may be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor DESIGN/BUILDER makes a Claim claim therefor as provided in this AgreementArticle 9.
Appears in 5 contracts
Samples: Construction Contract (Show Me Ethanol, LLC), Design/Build Agreement (Advanced BioEnergy, LLC), Design/Build Agreement (Husker Ag LLC)
Owner May Suspend Work. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor CON- TRACTOR and Architect ENGINEER which will fix the date on which Work will be resumed. Contractor CONTRACTOR shall resume the Work on the date so fixed. Contractor CONTRACTOR shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor CONTRACTOR makes a Claim therefor as provided in this Agreementparagraph 10.05.
Appears in 5 contracts
Samples: Maintenance Contract, Maintenance Contract, Hvac and Temperature Control Inspections and Service Contract
Owner May Suspend Work. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor and Architect which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed granted an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreementsuspension.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Owner May Suspend Work. At any time and without cause, Owner may suspend the Demolition Work or any portion thereof for a period of not more than ninety (90) consecutive days by notice in writing to Demolition Contractor and Architect which will fix the date on which Work will be resumed. Demolition Contractor shall resume the Demolition Work on the date so fixed. Demolition Contractor shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Demolition Contractor makes a Claim therefor therefore as provided in this Agreement.
Appears in 3 contracts
Samples: Demolition Contractor Services Agreement, Demolition Contractor Services Agreement, Demolition Contractor Services Agreement
Owner May Suspend Work. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than ninety (90) consecutive 90 days by notice in writing to Contractor and Architect DESIGN/BUILDER which will fix the date on which Work will be resumed. Contractor DESIGN/BUILDER shall resume the Work on the date so fixed. Contractor DESIGN/BUILDER shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor DESIGN/BUILDER makes a Claim claim therefor as provided in this AgreementArticle 9.
Appears in 2 contracts
Samples: Design/Builder Agreement (Western Plains Energy LLC), Design/Builder Agreement (Western Plains Energy LLC)
Owner May Suspend Work. A. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor CON- TRACTOR and Architect ENGINEER which will fix the date on which Work will be resumed. Contractor CONTRACTOR shall resume the Work on the date so fixed. Contractor CONTRACTOR shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor CONTRACTOR makes a Claim therefor as provided in this Agreementparagraph 10.05.
Appears in 1 contract
Samples: Maintenance Contract
Owner May Suspend Work.
A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by written notice in writing to Contractor and Architect which Engineer. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, Times directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreementsuspension. Any Change Proposal seeking such adjustments must be submitted no later than 30 days after the date fixed for resumption of Work.
Appears in 1 contract
Samples: Construction Contract
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor and Architect Project Administrator which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall may be allowed granted an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this AgreementParagraph 10.05.
Appears in 1 contract
Samples: Construction Contract
Owner May Suspend Work. A. At any time and without cause, Owner OWNER may suspend the Work or any portion thereof for a period of not more than ninety (90) consecutive days by notice in writing to Contractor and Architect DESIGN/BUILDER which will fix the date on which Work will be resumed. Contractor DESIGN/BUILDER shall resume the Work on the date so fixed. Contractor shall DESIGN/BUILDER may be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor DESIGN/BUILDER makes a Claim claim therefor as provided in this AgreementArticle 9.
Appears in 1 contract
Samples: Design/Build Agreement (East Kansas Agri Energy LLC)
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor Construction Manager and Architect which will fix the date on which Work will be resumedArchitect. Contractor Construction Manager shall resume the Work on the date so fixedUpon written notification from Owner. Contractor Construction Manager shall be allowed granted an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor Construction Manager makes a Claim therefor as provided in this AgreementParagraph 10.05.
Appears in 1 contract
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) consecutive 90 days by notice in writing to Contractor and Architect Design/Builder which will fix the date on which Work will be resumed. Contractor Design/Builder shall resume the Work on the date so fixed. Contractor Design/Builder shall be allowed an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor Design/Builder makes a Claim therefor therefore as provided in this AgreementArticle 9.
Appears in 1 contract
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by written notice in writing to Contractor and Architect which Engineer. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreementsuspension. Any Change Proposal seeking such adjustments shall be submitted no later than 30 days after the date fixed for resumption of Work.
Appears in 1 contract
Samples: Construction Contract
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 60 consecutive days by notice in writing to Contractor and Architect which Engineer. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, to the extent directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreementsuspension.
Appears in 1 contract
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 90 consecutive days by notice in writing to Contractor and Architect Engineer which will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed granted an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this AgreementParagraph 10.05.
Appears in 1 contract
Samples: Basic Form Agreement
Owner May Suspend Work. A. At any time and without cause, Owner may suspend the Work or any portion thereof for a period of not more than ninety (90) 60 consecutive days by written notice in writing to Contractor and Architect which Engineer. Such notice will fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. Contractor shall be allowed entitled to an adjustment in the Contract Price or an extension of the Contract Times, or both, directly attributable to any such suspension if Contractor makes a Claim therefor as provided in this Agreementsuspension.
Appears in 1 contract
Samples: Construction Contract