Common use of Owner Right to Correct or Complete Defective Work Clause in Contracts

Owner Right to Correct or Complete Defective Work. If Contractor fails to commence the Corrective Work within a reasonable period of time not to exceed ten (10) Days, or does not complete such Corrective Work on an expedited basis, then Owner, by written notice to Contractor, may (in addition to any other remedies that it has under this Agreement) correct such Defective Work, and Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) an amount equal to such reasonable costs and expenses; provided, however, if such Defective Work materially affects the construction, operation or use of any of the Work or the Facility or the Mirant Delta Facility or presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement) correct such Defective Work without giving prior written notice to Contractor (but shall give prompt notice to Contractor thereafter), and, in such event, Contractor shall be liable to Owner for all reasonable costs and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) an amount equal to such reasonable costs and expenses (which costs and expenses shall be adequately documented and supported by Owner).

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement (Mirant Corp), Engineering, Procurement and Construction Agreement (Mirant Corp)

AutoNDA by SimpleDocs

Owner Right to Correct or Complete Defective Work. If Contractor fails to commence the Corrective Work within a reasonable period of time not to exceed ten five (105) Days, or does not complete such Corrective Work on an expedited basis, then Owner, by written notice to Contractor, may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work, and Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, directly or by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses; provided, however, if such Defective Work materially affects the construction, operation or use of any of the Work or the Facility or the Mirant Delta Facility Project or presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work without giving prior written notice to Contractor (but shall give prompt notice to Contractor thereafter)Contractor, and, in such that event, Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, directly or by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses (which costs and expenses shall be adequately documented and supported by Owner)expenses.

Appears in 2 contracts

Samples: Construction Agreement (Cheniere Energy Inc), Construction Agreement (Cheniere Energy Inc)

Owner Right to Correct or Complete Defective Work. If Contractor fails to commence the Corrective Work within a reasonable period of time not to exceed ten forty-eight (1048) Dayshours, or does not complete such Corrective Work on an expedited basis, then Owner, by written notice to Contractor, may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work, and Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, by offset directly or by collection on the Contractor Letter of Creditoffset, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses; provided, however, if such Defective Work materially affects the construction, operation or use of any of the Work or the Facility or the Mirant Delta Facility Corpus Christi Pipeline Project or presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work without giving prior written notice to Contractor (but shall give prompt notice to Contractor thereafter)Contractor, and, in such that event, Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, by offset directly or by collection on the Contractor Letter of Creditoffset, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses (which costs and expenses shall be adequately documented and supported by Owner)expenses.

Appears in 1 contract

Samples: Construction Agreement (Cheniere Corpus Christi Holdings, LLC)

AutoNDA by SimpleDocs

Owner Right to Correct or Complete Defective Work. If Contractor fails to commence the Corrective Work within a reasonable period of time not to exceed ten forty-eight (1048) Dayshours, or does not complete such Corrective Work on an expedited basis, then Owner, by written notice to Contractor, may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work, and Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, directly or by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses; provided, however, if such Defective Work materially affects the construction, operation or use of any of the Work or the Facility or the Mirant Delta Facility Project or presents an imminent threat to the safety or health of any Person and Owner knows of such Defective Work, Owner may (in addition to any other remedies that it has under this Agreement, at law or in equity) correct such Defective Work without giving prior written notice to Contractor (but shall give prompt notice to Contractor thereafter)Contractor, and, in such that event, Contractor shall be liable to Owner for all reasonable costs costs, losses, damages and expenses incurred by Owner in connection with correcting such Defective Work and arising out of or relating to such Defective Work and shall pay Owner (directly, directly or by offset or by collection on the Contractor Letter of Credit, at Owner’s sole discretion) ), an amount equal to such reasonable costs costs, losses, damages and expenses (which costs and expenses shall be adequately documented and supported by Owner)expenses.

Appears in 1 contract

Samples: Construction Agreement (Cheniere Energy Inc)