Partial Acceptance. 24.3.1 If specified in the Contract, Installation and Commissioning shall be carried out individually for each identified major component or Subsystem(s) of the System. In this event, the provisions in the Contract relating to Installation and Commissioning, including the Operational Acceptance Test, shall apply to each such major component or Subsystem individually, and Operational Acceptance Certificates) shall be issued accordingly for each such major component or Subsystem of the System, subject to the limitations contained in GCC Clause 24.3.2.
Appears in 6 contracts
Samples: November 2013, October 2013, Contract
Partial Acceptance. 24.3.1 27.4.1 If specified in the Contract, Installation and Commissioning shall be carried out individually for each identified major component or Subsystem(s) of the System. In this event, the provisions in the Contract relating to Installation and Commissioning, including the Operational Acceptance Test, shall apply to each such major component or Subsystem individually, and Operational Acceptance CertificatesCertificate(s) shall be issued accordingly for each such major component or Subsystem of the System, subject to the limitations contained in GCC Clause 24.3.227.4.2.
Appears in 2 contracts
Samples: The Agreement (On Track Innovations LTD), The Agreement (On Track Innovations LTD)
Partial Acceptance. 24.3.1 27.4.1 If so specified in the ContractSCC for GCC Clause 27.2.1, Installation and Commissioning shall be carried out individually for each identified major component or Subsystem(s) of the System. In this event, the provisions in the Contract relating to Installation and Commissioning, including the Operational Acceptance Test, shall apply to each such major component or Subsystem individually, and Operational Acceptance CertificatesCertificate(s) shall be issued accordingly for each such major component or Subsystem of the System, subject to the limitations contained in GCC Clause 24.3.227.4.2.
Appears in 1 contract
Samples: www.zzozedo.ba