Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously. 42.2 The Engineer shall check the Contractor's monthly statement and within 14 days certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance). 42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractor. 42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed.. 42.5 The value of work executed shall include the valuation of Variations and Compensation Events. 42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 18 contracts
Samples: Construction Contract, Renovation Agreement, Construction Contract
Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor's monthly statement and within 14 days certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractor.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 8 contracts
Samples: Civil Works Agreement, Restructuring and Modernization Agreement, Construction Contract
Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previouslypreviously alongwith details of measurement of the quantity of works executed in a tabulated form as approved by the Engineer.
42.2 The Engineer shall check the Contractor's ’s monthly statement and within 14 days certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance)Contractor.
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractor.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill Xxxx of Quantities completed...
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 5 contracts
Samples: Project Agreement, Invitation for Bid (Ifb), Civil Works Agreement
Payment Certificates. 42.1 40.1. The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 40.2. The Engineer shall check the Contractor's Contractor‟s monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 40.3. The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 40.4. The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 40.5. The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 40.6. The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 2 contracts
Samples: Bid Document, Bid Document
Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor's monthly statement and within 14 days certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed..
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 2 contracts
Samples: Renovation Agreement, Restructuring and Modernisation Agreement
Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously...
42.2 The Engineer shall check the Contractor's monthly statement and within 14 days certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed..
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 2 contracts
Samples: Construction Contract, Restructuring & Modernisation of Distribution System of Bila Tank
Payment Certificates. 42.1 42.1. The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less les the cumulative amount certified previously.
42.2 42.2. The Engineer shall check the Contractor's ’s monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advanceadvance). The payment will be made according to the availability of fund.
42.3 42.3. The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 42.4. The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 42.5. The value of work executed shall include the valuation of Variations variations and Compensation Events.
42.6 42.6. The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Bidding Document
Payment Certificates. 42.1 42.1. The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less les the cumulative amount certified previously.
42.2 42.2. The Engineer shall check the Contractor's ’s monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advanceadvance). The payment will be made according to the availability of fund.
42.3 42.3. The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorManaging Director, ASTC.
42.4 42.4. The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 42.5. The value of work executed shall include the valuation of Variations variations and Compensation Events.
42.6 42.6. The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Construction Contract
Payment Certificates. 42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previouslypreviously along with details of measurement of the quantity of works executed in a tabulated form as approved by the Engineer.
42.2 The Engineer shall check the details given in the Contractor's monthly statement and within 14 days certify the amount amounts to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).month
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractor.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Construction Contract
Payment Certificates. 42.1 The Contractor contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor's ’s monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works work in the relevant amounts and under conditions set forth in sub-clause Sub- Clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed..Completed.
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Tender Agreement
Payment Certificates. 42.1 42.1. The Contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 42.2. The Engineer shall check the Contractor's monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works in the relevant amounts and under conditions set forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 42.3. The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 42.4. The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed...
42.5 42.5. The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 42.6. The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Procurement Agreement
Payment Certificates. 42.1 The Contractor contractor shall submit to the Engineer monthly statements of the estimated value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor's ’s monthly statement and within 14 days and certify the amount to be paid to the Contractor after taking into account any credit or debit for the month in question in respect of materials for the works work in the relevant amounts and under conditions set forth in subSub-clause Clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the quantities claimed as executed by the contractorEngineer.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of Quantities completed..Completed.
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.
Appears in 1 contract
Samples: Construction Contract