Payment Milestone. 1: payment of Euro 680.00 per kWp (six hundreds eighty), with deduction of Euro 10,000.00 (ten thousand) referred to in Recital (F) and of the deposit equal to Euro 25,000.00 (twenty five thousand) referred to in Recital (I), shall become due by the Principal on occurrence of all the following events: i. completion of the Building Permit and all Applicable Permits (excluding the Incentive) procedure, including submission of the variations, if any, consequent to the planning and Equipment amendments, and the performance of the provisions established by the competent municipal technical offices to which the Building Permit might be subject to; ii. transfer to the Principal or a third company indicated by the Principal of the relevant Land Use Rights, by way of assignment of the definitive Land Use Right contract or by any other way as the Principal may require; iii. connection of the System to the grid is reasonably estimated by the Contractor, by way of a statement drafted in accordance with Annex 13 to take place within 120 (hundred and twenty) days; iv. delivery of the Parent Company Guarantee in compliance with the last paragraph of this Article 4.2, letter a). Promptly after payment of the relevant invoice, and in any case within 45 days of receipt thereof by the Principal, the Contractor shall provide evidence to the Principal that the Building Permit as well as the STMC (and of any Applicable Permit already obtained) have been successfully transferred to the Principal. The Contractor undertakes to deliver to the Principal, the Parent Company Guarantee within 7 (seven) Working Days of execution of this Contract, and in any case before having received the payment. The Parent Company Guarantee will be issued for the due performance of the Works, as well as for the due performance by the Contractor of any and all the obligations undertaken under this Contract, including, but not limited to, (i) the obtaining of a valid title of Land Use Right over the land where the System shall be built and developed in accordance to Article 3 above; (ii) the obtaining of all the Applicable Permits required for the construction, connection and the functioning of the System; (iii) the transfer of the Building Permit in favour of the Principal; (iv) the admission to the Incentives; and (v) any and all payment obligations arising in connection herewith. The Parent Company Guarantee will be issued in the form under Annex 5, for an amount equal to the Consideration. From the execution date by the Principal of the PAC, the Parent Company Guarantee must also guarantee the precise and prompt performance of the obligations undertaken by the Contractor, pursuant to the O&M Agreement, as well as the punctual performance of all the payment obligations, borne by the Contractor under the O&M Contract. The Parent Company Guarantee shall be finally released upon issuance of the FAC.
Appears in 2 contracts
Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)
Payment Milestone. 1: payment of Euro 680.00 per kWp (six hundreds eighty), with deduction of Euro 10,000.00 (ten thousand) referred to in Recital (F) and of the deposit equal to Euro 25,000.00 (twenty five thousand) referred to in Recital (I), shall become due by the Principal on occurrence of all the following events:
i. completion of the Building Permit and all Applicable Permits (excluding the Incentive) procedure, including submission of the variations, if any, consequent to the planning and Equipment amendments, and the performance of the provisions established by the competent municipal technical offices to which the Building Permit might be subject to;
ii. transfer to the Principal or a third company indicated by the Principal of the relevant Land Use Rights, by way of assignment of the definitive Land Use Right contract or by any other way as the Principal may require;
iii. connection of the System to the grid is reasonably estimated by the Contractor, by way of a statement drafted in accordance with Annex 13 to take place within 120 (hundred and twenty) days;
iv. delivery of the Parent Company Guarantee in compliance with the last paragraph of this Article 4.2, letter a). Promptly after payment of the relevant invoice, and in any case within 45 days of receipt thereof by the Principal, the Contractor shall provide evidence to the Principal that the Building Permit as well as the STMC (and of any Applicable Permit already obtained) have been successfully transferred to the Principal. The Contractor undertakes to deliver to the Principal, the Parent Company Guarantee within 7 (seven) Working Days of execution of this Contract, and in any case before having received the payment. The Parent Company Guarantee will be issued for the due performance of the Works, as well as for the due performance by the Contractor of any and all the obligations undertaken under this Contract, including, but not limited to, (i) the obtaining of a valid title of Land Use Right over the land where the System shall be built and developed in accordance to Article 3 above; (ii) the obtaining of all the Applicable Permits required for the constructionrealization, connection and the functioning of the System; (iii) the transfer of the Building Permit in favour of the Principal; (iv) the admission to the Incentives; and (v) any and all payment obligations arising in connection herewith. The Parent Company Guarantee will be issued in the form under Annex 5, for an amount equal to the Consideration. From the execution date by the Principal of the PAC, the Parent Company Guarantee must also guarantee the precise and prompt performance of the obligations undertaken by the Contractor, pursuant to the O&M Agreement, as well as the punctual performance of all the payment obligations, borne by the Contractor under the O&M Contract. The Parent Company Guarantee shall be finally released upon issuance of the FAC.
Appears in 2 contracts
Samples: Engineering Procurement & Construction Contract (Ellomay Capital Ltd.), Engineering Procurement & Construction Contract (Ellomay Capital Ltd.)