Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. 40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work. 40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs. 40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event. 40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 31 contracts
Samples: Construction Contract, Renovation Agreement, Renovation Agreement
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 5 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill Xxxx of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill Xxxx of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer Engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that which could have been avoided by giving early warning.
Appears in 5 contracts
Samples: Project Agreement, Invitation for Bid (Ifb), Civil Works Agreement
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer Engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that which could have been avoided by giving early warning.
Appears in 3 contracts
Samples: Project Agreement, Procurement Agreement, Project Agreement
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill Xxxx of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill Xxxx of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 3 contracts
Samples: Construction Contract, Punjab Rural Water Supply & Sanitation Project Agreement, Punjab Rural Water Supply & Sanitation Project Agreement
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill Xxxx of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill Xxxx of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer Engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s Engineer‟s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that which could have been avoided by giving early warning.
Appears in 2 contracts
Samples: Bidding Agreement, Bidding Agreement
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause Clause
38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 2 contracts
Samples: Construction Contract, Restructuring & Modernisation of Distribution System of Bila Tank
Payments for Variations. 40.1 40.1. The Contractor shall provide the Engineer with a quotation (with breakdown break down of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. The Engineer shall send the rate so assessed to the Chief Engineer, P.W.D. (Bldg), Assam for approval.
40.2 40.2. If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the the; timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Bill of Quantities quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 40.3. If the Contractor's ’s quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),unreasonable, the Engineer may order the Variation and make a change to the Contract Price Price, which shall be based on Engineer’s own forecast forecaster of the effects of the Variation on the Contractor's ’s costs.
40.4 40.4. If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no the Engineer shall allow the contractor to proceed with the work using materials having I.S. marks/ approved brand as specified in the A.P.W.D. S.O.R. obtained from approved dealers of the company. The Engineer shall collect the quotation shall be given for himself and assess the Variation shall be treated as a Compensation Eventcost/ rate of the item considering all aspects and submit the same to the Chief Engineer, PWD (Bldg), Chandmari, Guwahati-3, Assam for approval.
40.5 40.5. The Contractor shall not be entitled to additional payment for costs that costs, which could have been avoided by giving early warning.
Appears in 1 contract
Samples: Bid Document
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause Clause
38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 1 contract
Samples: Construction Contract
Payments for Variations. 40.1 40.1. The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. The Engineer shall send the rate so assessed to the Managing Director, ASTC ,Paltanbazar, Guwahati-8 for approval.
40.2 40.2. If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the the; timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Bill of Quantities quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 40.3. If the Contractor's ’s quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),unreasonable, the Engineer may order the Variation and make a change to the Contract Price Price, which shall be based on Engineer’s own forecast forecaster of the effects of the Variation on the Contractor's ’s costs.
40.4 40.4. If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no the Engineer shall allow the contractor to proceed with the work using materials having I.S. marks/ approved brand as specified in the A.P.W.D. S.O.R. obtained from approved dealers of the company. The Engineer shall collect the quotation shall be given for himself and assess the Variation shall be treated as a Compensation Eventcost/ rate of the item considering all aspects and submit the same to the Managing Director, ASTC ,Paltanbazar, Guwahati-8 for approval.
40.5 40.5. The Contractor shall not be entitled to additional payment for costs that costs, which could have been avoided by giving early warning.
Appears in 1 contract
Samples: Construction Contract
Payments for Variations. 40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s Engineer‘s own forecast of the effects of the Variation on the Contractor's costs.
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 1 contract
Samples: Construction Contract
Payments for Variations. 40.1 40.1. The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 40.2. If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Bill of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 40.3. If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),unreasonable, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s 's own forecast of the effects of the Variation on the Contractor's costs.
40.4 40.4. If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 40.5. The Contractor shall not be entitled to additional payment for costs that which could have been avoided by giving early warning.
Appears in 1 contract
Samples: Procurement Agreement
Payments for Variations. 40.1 40.1. The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered. The Engineer shall send the rate so assessed to the Managing Director, ASDC for SC Ltd, Dispur, Guwahati-6, for approval.
40.2 40.2. If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the the; timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill Bill of Quantities quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill of Quantities, the quotation by the Contractor shall be in the form of new rates for the relevant items of work.
40.3 40.3. If the Contractor's ’s quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),unreasonable, the Engineer may order the Variation and make a change to the Contract Price Price, which shall be based on Engineer’s own forecast forecaster of the effects of the Variation on the Contractor's ’s costs.
40.4 40.4. If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no the Engineer shall allow the contractor to proceed with the work using materials having I.S. marks/ approved brand as specified in the A.P.W.D. S.O.R. obtained from approved dealers of the company. The Engineer shall collect the quotation shall be given for himself and assess the Variation shall be treated as a Compensation Eventcost/ rate of the item considering all aspects and submit the same to the Managing Director, ASDC for SC Ltd, Dispur, Guwahati-6 for approval.
40.5 40.5. The Contractor shall not be entitled to additional payment for costs that costs, which could have been avoided by giving early warning.
Appears in 1 contract
Samples: Bidding Document
Payments for Variations. 40.1 36.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation, which shall be given within seven days of the request or within any longer period stated by the Engineer and before the Variation is ordered.
40.2 36.2 If the work in the Variation corresponds with an item description in the Bill Xxxx of Quantities and if, in the opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of its execution do not cause the cost per unit of quantity to change, the rate in the bill xxxx of Quantities shall be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or timing of the work in the Variation does not correspond with items in the Bill Xxxx of Quantities, the quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 36.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a quotation within a reasonable time specified by the engineer in accordance with Clause 40.1),, the Engineer may order the Variation and make a change to the Contract Price which shall be based on Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
40.4 36.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and considered without delaying the work, no quotation shall be given and the Variation shall be treated as a Compensation Event.
40.5 36.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by giving early warning.
Appears in 1 contract
Samples: Construction Contract