Common use of PRE-COMMISSIONING TESTS Clause in Contracts

PRE-COMMISSIONING TESTS. On completion of erection of the equipment and before charging, each item of the equipment shall be thoroughly cleaned and then inspected jointly by the Employer and the contractor for correctness and completeness of installation and acceptability for charging, leading to initial pre-commissioning tests at Site. The list of pre- commissioning tests to be performed is given in respective chapters or as included in the Contractor’s quality assurance programme.

Appears in 28 contracts