The Pre-Resolution Procedure clause establishes a mandatory process that parties must follow before initiating formal dispute resolution methods, such as litigation or arbitration. Typically, this involves steps like written notice of the dispute, a period for negotiation or mediation, and possibly escalation to higher management. By requiring these preliminary steps, the clause encourages parties to resolve disagreements amicably and efficiently, reducing the likelihood of costly and time-consuming legal proceedings.
Pre-Resolution Procedure. A Contractor raising an issue related to a breach of contract or an issue concerning time or money shall file a Pre Resolution request to County Project Manager as a prerequisite for any consideration of the issue by the County. The Pre-Resolution is subject to approval by County District Attorney Office as necessary.
42.1.1 The Pre-Resolution request must be filed in writing by Contractor with the County Project Manager within twenty-one (21) days of issuance of the occurrence in which Contractor disagrees with such assessment or an issuance of a denial of a written request by Contractor for additional monies or time.
42.1.2 County shall issue to Contractor a written decision providing the basis for the decision of the issues presented by all of the parties within thirty (30) days of receipt of all of the information required by County in Section 18.0.
Pre-Resolution Procedure. A Contractor raising an issue related to a breach of contract or an issue concerning time or money shall file a Pre Resolution request to County Project Manager as a prerequisite for any consideration of the issue by the County. .
42.1.1 The Pre-Resolution request must be filed in writing by Contractor with the County Project Manager within twenty-one (21) days of issuance of the occurrence in which Contractor disagrees with such assessment or an issuance of a denial of a written request by Contractor for additional monies or time.
42.1.2 County shall issue to Contractor a written decision providing the basis for the decision of the issues presented by all of the parties within thirty (30) days of receipt of all of the information required by County in Section 18.0.
Pre-Resolution Procedure. The Owner Representative may request additional information and may meet with the parties involved with the issue.
Pre-Resolution Procedure. The DFCM Representative may request additional information and may meet with the parties involved with the issue.