Procedure Following Inspections. Following each handback inspection under Section 8.2, the Contractor shall within: (a) 60 days of the first handback inspection; (b) 30 days of the second handback inspection; and (c) 7 days of the third handback inspection; prepare and deliver to the Province a comprehensive workplan and schedule acceptable to the Province, acting reasonably, designed to ensure that the New Infrastructure and the Existing Infrastructure will meet the Handback Requirements upon expiry of the Term. Following delivery and acceptance of such workplan and schedule, the Contractor shall keep the Province fully advised of all activity and progress in carrying out the workplan.
Appears in 4 contracts
Samples: Design, Build, Finance and Operate Agreement, Dbfo Agreement, Design, Build, Finance and Operate Agreement
Procedure Following Inspections. Following each handback inspection under Section 8.2, the Contractor shall within:
(a) 60 days of the first handback inspection;
(b) 30 days of the second handback inspection; and
(c) 7 days of the third handback inspection; prepare and deliver to the Province a comprehensive workplan and schedule acceptable to the Province, acting reasonably, designed to ensure that the New Infrastructure and the Existing Infrastructure will meet the Handback Requirements upon expiry of the Term. Following delivery and acceptance of such workplan and schedule, the Contractor shall keep the Province fully advised of all activity and progress in carrying out the workplan.
Appears in 1 contract
Procedure Following Inspections. Following each handback inspection under Section 8.2, the Contractor shall within:
(a) 60 days of the first handback inspection;
(b) 30 days of the second handback inspection; and
(c) 7 days of the third handback inspection; prepare and deliver to the Province a comprehensive workplan and schedule acceptable to the Province, acting reasonably, designed to ensure that the New Infrastructure and the Existing Infrastructure Schools will meet the Handback Requirements upon expiry of the Term. Following delivery and acceptance of such workplan and schedule, the Contractor shall keep the Province fully advised of all activity and progress in carrying out the workplan.
Appears in 1 contract