Procedure for claiming relief. Without prejudice to Clause 17.3, an Affected Party is only entitled to claim force majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 and to perform its obligations under Clause 17.6.
Appears in 63 contracts
Samples: www.orr.gov.uk, www.orr.gov.uk, www.orr.gov.uk
Procedure for claiming relief. Without prejudice to Clause 17.3, an Affected Party is only entitled to claim force majeure Force Majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 and to perform its obligations under Clause 17.6.
Appears in 46 contracts
Samples: Track Access Contract, Track Access Contract, Track Access Contract
Procedure for claiming relief. Without prejudice to Clause clause 17.3, an Affected Party is only entitled to claim force majeure Force Majeure relief under this Clause clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause clause 17.5 and to perform its obligations under Clause clause 17.6.
Appears in 42 contracts
Samples: www.orr.gov.uk, www.orr.gov.uk, www.orr.gov.uk
Procedure for claiming relief. Without prejudice to Clause 17.317.2, an Affected Party is only entitled to claim force majeure Force Majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 17.4 and to perform its obligations under Clause 17.617.5.
Appears in 18 contracts
Samples: Connection Contract, Connection Contract, www.orr.gov.uk
Procedure for claiming relief. Without prejudice to Clause 17.3, an Affected Party is only entitled to claim force majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 and to perform its obligations under Clause 17.6.
Appears in 2 contracts
Samples: www.orr.gov.uk, www.orr.gov.uk
Procedure for claiming relief. Without prejudice to Clause 17.317.2, an Affected Party is only entitled to claim force majeure relief for a Force Majeure Event under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 17.4 and to perform its obligations under Clause 17.617.5.
Appears in 2 contracts
Samples: Connection Agreement, Connection Agreement
Procedure for claiming relief. Without prejudice to Clause 17.314.3, an Affected Party is only entitled to claim force majeure relief under this Clause 17 14 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 14.5 and to perform its obligations under Clause 17.614.6.
Appears in 1 contract
Samples: Track Access Contract
Procedure for claiming relief. Without prejudice to Clause 17.317.2, an Affected Party is only entitled to claim force majeure Force Majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 17.4 and to perform its obligations under Clause 17.617.5.
Appears in 1 contract
Samples: Connection Contract
Procedure for claiming relief. Without prejudice to Clause 17.3, an Affected Party is only entitled to claim force majeure Force Majeure relief under this Clause 17 if it complies with the obligations to give Force Majeure Notices, Force Majeure Reports and provide other information under Clause 17.5 and to perform its obligations under Clause 17.6.17.6.
Appears in 1 contract
Samples: Track Access Contract