PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (2-20-07) (Rev. 3-19-13) 105-16, 230, 801 SP1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor shall do all of the following:

Appears in 21 contracts

Samples: Roadway Contract, Roadway & Structure Contract, Roadway Contract

AutoNDA by SimpleDocs

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (2-20-07) (Rev. 34-5-19-13) 105-16, 230, 801 SP1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor shall do all of the following:

Appears in 6 contracts

Samples: Roadway Contract, Roadway Contract, Roadway Contract

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (21-2022-0713) (Rev. 39-197-1317) 105-16, 230, 801 SP1 DB1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor Design- Build Team shall do all of the following:

Appears in 3 contracts

Samples: Contract, Contract, Roadway & Structure Contract

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (2-20-07) (Rev. 3-1920-13) 105-16, 230, 801 SP1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor shall do all of the following:

Appears in 2 contracts

Samples: Construction Contract, Contract/Agreement

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (2-20-07) (Rev. 3-19-13) 105-16, 230, 801 SP1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural tonatural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor shall do all of the following:

Appears in 1 contract

Samples: Roadway Contract

AutoNDA by SimpleDocs

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (21-20-07) (Rev. 3-1922-13) 105-16, 230, 801 SP1 DB1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor Design- Build Team shall do all of the following:

Appears in 1 contract

Samples: Roadway & Structure Contract

PROCEDURE FOR MONITORING BORROW PIT DISCHARGE. (2-20-07) (Rev. 3-19-13) 105-16, 230, 801 SP1 DB1 G181 Water discharge from borrow pit sites shall not cause surface waters to exceed 50 NTUs (nephelometric turbidity unit) in streams not designated as trout waters and 10 NTUs in streams, lakes or reservoirs designated as trout waters. For lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTUs. If the turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. If during any operating day, the downstream water quality exceeds the standard, the Contractor Design- Build Team shall do all of the following:

Appears in 1 contract

Samples: Construction Contract