Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's Applications for Payment, on or about the 1st day of each month during performance of the Work as provided in paragraphs 5.01.B.1 and B.2 below. All such payments will be measured by the acceptable Schedule of Values established in paragraph 2.06.A of the General Conditions.
Appears in 1 contract
Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDERCONTRACTOR's Applications for Payment, Payment on or about the 1st 15th day of each month during performance of the Work as provided in paragraphs 5.01.B.1 5.02(1)(A) and B.2 below5.02(1)(B). All such payments will be measured by the acceptable Schedule schedule of Values established in paragraph 2.06.A of the General Conditions.values indicated:
Appears in 1 contract
Samples: Contract Agreement
Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDERCONTRACTOR's Applications for Payment, Payment on or about the 1st day of each month during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A. 1 and B.2 6.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A of the General Conditions.Contract Documents:
Appears in 1 contract
Samples: Contract Agreement
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’s Applications for Payment, Payment on or about the 1st 25th day of each month during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A.1 and B.2 6.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Samples: Form of Agreement
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’S Applications for Payment, on or about the 1st day of each month Payment every two (2) weeks during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A.1 and B.2 6.02.A.2 below. Payments for work completed shall be made within fifteen (15) days of submission of application for payment. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’s Applications for Payment, Payment on or about the 1st 15th day of each month during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A.1 and B.2 6.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Samples: Construction Agreement
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’s Applications for Payment, Payment on or about the 1st day of each month during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A.1 and B.2 6.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’s Applications for Payment, Payment on or about the 1st day of each month during performance of the Work as provided in paragraphs 5.01.B.1 4.02.A.1 and B.2 4.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Samples: E Energy Adams LLC
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’S Applications for Payment, Payment on or about the 1st last day of each month during performance of the Work as provided in paragraphs 5.01.B.1 6.02.A.1 and B.2 6.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Samples: Agreement (E Energy Adams LLC)
Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's Applications for Payment, on or about the 1st day of each month during performance of the Work as provided in paragraphs 5.01.B.1 5.01.A.1 and B.2 A.2 below. All such payments will be measured by the acceptable Schedule of Values established in paragraph 2.06.A of the General Conditions.
Appears in 1 contract
Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDER's CONTRACTOR’s Applications for Payment, Payment on or about the 1st 15th day of each month during performance of the Work as provided in paragraphs 5.01.B.1 4.02.A.1 and B.2 4.02.A.2 below. All such payments will be measured by the acceptable Schedule schedule of Values values established in paragraph 2.06.A 2.07.A of the General Conditions.Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements:
Appears in 1 contract
Samples: E Energy Adams LLC
Progress Payments; Retainage. OWNER shall make progress payments on account of the Contract Price on the basis of DESIGN/BUILDERCONTRACTOR's Applications for Payment, Payment on or about the 1st 15th day of each month during performance of the Work as provided in paragraphs 5.01.B.1 5.02(l)(A) and B.2 below5.02(l)(B). All such payments will be measured by the acceptable Schedule schedule of Values established in paragraph 2.06.A of the General Conditions.values indicated:
Appears in 1 contract
Samples: Contract Agreement