Progressive Operations. PURCHASER shall complete the following requirements on each setting prior to moving to a new setting, unless otherwise approved in writing by STATE: (a) Remove all logs as described under Section 45, "Log Removal." (b) Construct cross-drainage ditches or waterbars as directed by STATE. (c) Block roads and skid trails to vehicular traffic as directed by STATE. In addition, PURCHASER shall complete the following requirements within the following time frames, unless otherwise approved in writing by STATE: (1) Complete all felling requirements as required by the section titled, “Felling,” within 14 calendar days after completion of yarding activities. (2) Complete snag creation as required by the section titled, “Snag Creation,” within 30 calendar days after completion of yarding activities. (3) Remove all trash from the timber sale area within 14 calendar days after completion of log hauling activities. (4) Remove all equipment and materials from the timber sale area within 30 calendar days after completion of log hauling activities. See Section 23, "Removal of Equipment and Materials." (5) Complete road maintenance requirements of the sections titled, “Access” and “Road Maintenance,” within 30 calendar days after completion of log hauling activities. (6) Remove right-of-way logs from a road segment prior to subgrade approval. FIRE CONTROL AND SLASH DISPOSAL
Appears in 1 contract
Samples: Timber Sale Contract
Progressive Operations. PURCHASER shall complete the following requirements on each setting prior to moving to a new setting, unless otherwise approved in writing by STATE:
(a) Remove all logs as described under Section 45, "Log Removal."
(b) Construct cross-drainage ditches or waterbars as directed by STATE.
(c) Block Extend 12 hours of shovel time to block roads and skid trails to vehicular traffic as directed by STATE.
(d) Expend up to 8 hours with a log loader retrieving large woody debris from landing slash and stacking it on the landing, as directed by STATE. In addition, PURCHASER shall complete the following requirements within the following time frames, unless otherwise approved in writing by STATE:
(1) Complete all felling requirements as required by the section titled, “Felling,” within 14 calendar days after completion of yarding activities, but prior to March 15, 2005.
(2) Complete snag creation as required by the section titled, “Snag Creation,” within 30 calendar days after completion of yarding activities.
(3) Remove all trash from the timber sale area within 14 calendar days after completion of log hauling activities.
(43) Remove all equipment and materials from the timber sale area within 30 calendar days after completion of log hauling activities. See Section 23, "Removal of Equipment and Materials."
(54) Complete road maintenance requirements of the sections titled, “Access” and “Road Maintenance,” within 30 calendar days after completion of log hauling activities.
(65) Remove right-of-way logs from a road segment prior to subgrade approval. FIRE CONTROL AND SLASH DISPOSAL
Appears in 1 contract
Samples: Timber Sale Contract
Progressive Operations. PURCHASER shall complete the following requirements on each setting timber sale area prior to moving to a new settingtimber sale area, unless otherwise approved in writing by STATE:
(a) Remove all logs as described under Section 45, "Log Removal."
(b) Construct cross-drainage ditches or waterbars as specified in Exhibit F and as directed by STATE.
(c) Block roads and skid trails to vehicular traffic as directed by STATE. In addition, PURCHASER shall complete the following requirements within the following time frames, unless otherwise approved in writing by STATE:
(1) Complete all felling requirements as required by the section titled, “Felling,” within 14 calendar days after completion of yarding activities.
(2) Complete snag creation as required by the section titled, “Snag Creation,” within 30 calendar days after completion of yarding activities.
(3) Remove all trash from the timber sale area within 14 calendar days after completion of log hauling activities.
(4) Remove all equipment and materials from the timber sale area within 30 calendar days after completion of log hauling activities. See Section 23, "Removal of Equipment and Materials."
(52) Complete road maintenance requirements of the sections titled, “Access” and “Road Maintenance,” within 30 14 calendar days after completion of log hauling activities.
(63) Remove right-of-way logs from a road segment prior to subgrade approvalComplete the requirements of the section titled, "Recreation Trail Protection" within 14 calendar days after completion of log hauling on each timber sale area. FIRE CONTROL AND SLASH DISPOSAL
Appears in 1 contract
Samples: Timber Sale Contract
Progressive Operations. PURCHASER shall complete the following requirements on each setting timber sale area prior to moving to a new settingtimber sale area, unless otherwise approved in writing by STATE:
(a) Remove all logs as described under Section 45, "Log Removal."
(b) Construct cross-drainage ditches or waterbars as specified in Exhibit F and as directed by STATE.
(c) Block roads and skid trails to vehicular traffic as directed by STATE. In addition, PURCHASER shall complete the following requirements within the following time frames, unless otherwise approved in writing by STATE:
(1) Complete all felling requirements as required by the section titled, “Felling,” within 14 calendar days after completion of yarding activities.
(2) Complete snag creation as required by the section titled, “Snag Creation,” within 30 calendar days after completion of yarding activities.
(3) Remove all trash from the timber sale area within 14 calendar days after completion of log hauling activities.
(4) Remove all equipment and materials from the timber sale area within 30 calendar days after completion of log hauling activities. See Section 23, "Removal of Equipment and Materials."
(52) Complete road maintenance requirements of the sections titled, “Access” and “Road Maintenance,” within 30 14 calendar days after completion of log hauling activities.
(63) Remove right-of-way logs from a road segment prior to subgrade approval. Complete the requirements of the section titled, “Recreation Trail Protection,” within 14 calendar days after completion of log hauling on Area I. FIRE CONTROL AND SLASH DISPOSAL
Appears in 1 contract
Samples: Timber Sale Contract
Progressive Operations. PURCHASER shall complete the following requirements on each setting prior to moving to a new setting, unless otherwise approved in writing by STATE:
(a) Remove all logs as described under Section 45, "Log Removal."
(b) Construct cross-drainage ditches or waterbars as specified in Exhibit F and as directed by STATE.
(c) Block roads and skid trails to vehicular traffic as directed by STATE. In addition, PURCHASER shall complete the following requirements within the following time frames, unless otherwise approved in writing by STATE:
(1) Complete all felling requirements as required by the section titled, “Felling,” within 14 calendar days after completion of yarding activities.
(2) Complete snag creation Construct fire trails as required by the section titled, “Snag CreationFire Trails,” within 30 calendar days after completion of yarding activities.
(3) Remove all trash from the timber sale area within 14 30 calendar days after completion of log hauling activities.
(4) Remove all equipment and materials from the timber sale area within 30 calendar days after completion of log hauling activities. See Section 23, "Removal of Equipment and Materials."
(5) Complete road maintenance requirements of the sections titled, “Access” and “Road Maintenance,” within 30 14 calendar days after completion of log hauling activities.
(6) Remove right-of-way logs from a road segment prior to subgrade approval. FIRE CONTROL AND SLASH DISPOSAL
Appears in 1 contract