Project Approvals Action Plan. 3.3.1. Contractor shall confer with Contract Administrator and Consultant to jointly develop a “Project Approvals Action Plan” for obtaining all site plan approvals, development orders, permits, licenses and other approvals from all agencies with jurisdiction over the project. 3.3.1.1. This plan shall verify and further develop preliminary information that may have been developed by either Contract Administrator and/or Consultant. Contract Administrator and/or Consultant will make their preliminary documentation available to Contractor. Project Approvals Action Plan shall confirm and include a listing of those regulatory and/or jurisdictional agencies with authority over the Project, document submittal requirements, application and permit fees, anticipated review times, duration/expiration periods for any issued approval(s), and the party responsible for making submittal of documents and fees related to any approval, review or licensure. 3.3.1.2. Contractor shall include scheduling information derived from the “Project Approvals Action Plan” into Project schedules further described below and shall coordinate with Contract Administrator and Consultant concerning optimum timing for submittals, corrections, reviews and other milestone dates/periods pertinent to the Project approvals process. 3.3.1.3. Contractor shall submit (5) copies of the Project Approvals Action Plan to Contract Administrator prior to Consultant’s submittal of Design Development. 3.3.1.4. Upon discovery of changes to building codes, regulatory agencies and other jurisdictional requirements that impact the project, Contractor shall advise Contract Administrator and Consultant and modify the “Project Approvals Action Plan” on an as needed basis to ensure the project’s continued and future compliance with the process for obtaining jurisdictional approvals.
Appears in 2 contracts
Samples: Construction Agreement, Construction Agreement
Project Approvals Action Plan. 3.3.1. Contractor shall confer with Contract Administrator and Consultant to jointly develop a “Project Approvals Action Plan” for obtaining all site plan approvals, development orders, permits, licenses and other approvals from all agencies with jurisdiction over the project.
3.3.1.1. This plan shall verify and further develop preliminary information that may have been developed by either Contract Administrator and/or or Consultant. Contract Administrator and/or or Consultant will make their preliminary documentation available to Contractor. Project Approvals Action Plan shall confirm and include a listing of those regulatory and/or or jurisdictional agencies with authority over the Project, document submittal requirements, application and permit fees, anticipated review times, duration/expiration periods for any issued approval(s), and the party responsible for making submittal of documents and fees related to any approval, review or licensure.
3.3.1.2. Contractor shall include scheduling information derived from the “Project Approvals Action Plan” into Project schedules further described below and shall coordinate with Contract Administrator and Consultant concerning optimum timing for submittals, corrections, reviews and other milestone dates/periods pertinent to the Project approvals process.
3.3.1.3. Contractor shall submit (5) copies of the Project Approvals Action Plan to Contract Administrator prior to Consultant’s submittal of Design Development.
3.3.1.4. Upon discovery of changes to building codes, regulatory agencies and other jurisdictional requirements that impact the project, Contractor shall advise Contract Administrator and Consultant and modify the “Project Approvals Action Plan” on an as needed basis to ensure the project’s continued and future compliance with the process for obtaining jurisdictional approvals.