Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:
Appears in 13 contracts
Samples: Escrow Agreement, Procurement and Construction Agreement (Cheniere Corpus Christi Holdings, LLC), Procurement and Construction Agreement (Corpus Christi Pipeline GP, LLC)
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject 5 safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:
Appears in 2 contracts
Samples: Escrow Agreement (Cheniere Energy Partners, L.P.), Escrow Agreement (Cheniere Energy Partners, L.P.)
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures procedure the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject Project 5 safely and in accordance with Attachment V 22 of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:: Execution Copy Phase 4
Appears in 1 contract
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures procedure the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject Project 1 and Project 2 safely and in accordance with Attachment V 22 of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:: Execution Copy Phase 1
Appears in 1 contract
Samples: Procurement and Construction Agreement (Tellurian Inc. /De/)
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures procedure the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject Project 4 safely and in accordance with Attachment V 22 of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:: Execution Copy Phase 3
Appears in 1 contract
Samples: Procurement and Construction Agreement (Tellurian Inc. /De/)
Project Commissioning Plan. A. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that for the Equipment is brought through pre-commissioning, commissioning, Start Upstart-up, Performance Tests and Substantial Completion of each Subproject safely and Train in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:M.
Appears in 1 contract
Samples: Engineering, Procurement and Construction Agreement (Cheniere Energy, Inc.)
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:: Execution Version
Appears in 1 contract