Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum: a. Mechanical completion; b. Field testing; c. Ready for Start Up; d. Commissioning; e. Development of operating manuals; f. Development of maintenance manuals; g. Ready for Performance Testing; h. Performance Testing; i. Emissions and noise testing; j. Interface with the FERC as required in accordance with Section 9; k. Substantial Completion Punchlist of each Subproject; l. Close-out; and
Appears in 3 contracts
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners LP Holdings, LLC), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:
a. Mechanical completion;
b. Field testing;
c. Ready for Start Up;
d. Commissioning;
e. Development of operating manuals;
f. Development of maintenance manuals;
g. Ready for Performance Testing;
h. Performance Testing;
i. Emissions and noise testing;
j. Interface with the FERC as required in accordance with Section 9;
k. Substantial Completion Punchlist of each Subproject;
l. Close-out; and
Appears in 1 contract
Samples: Lump Sum Turnkey Agreement
Project Commissioning Plan. Contractor shall produce a detailed plan (“Project Commissioning Plan”) for review by Owner. The Project Commissioning Plan shall list the procedures the Contractor intends to use to ensure that Equipment is brought through pre-commissioning, commissioning, Start Up, Performance Tests and Substantial Completion of each Subproject safely and in accordance with Attachment V of the Agreement. The Project Commissioning Plan will be implemented by Contractor, and address the following as a minimum:
a. Mechanical completion;
b. Field testing;
c. Ready for Start UpUp of Subproject 6 (a);
d. Commissioning;
e. Development of operating manuals;
f. Development of maintenance manuals;
g. Ready for Performance TestingTesting of Subproject 6(a);
h. Performance TestingTesting of Subproject 6(a);
i. Emissions and noise testing;
j. Interface with the FERC as required in accordance with Section 9;
k. Substantial Completion Punchlist of each Subprojectfor Subproject 6;
l. Close-out; and
Appears in 1 contract
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC)