Project Milestone-II. 2.1 Project Milestone-II shall occur on or before 6 (six) months from the Appointed Date (the “Project Milestone-II”) upon completion of 25% of civil construction works 2.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have completed building civil construction framing works upto terrace floor including headroom, fluid structure foundation and approval of all shop drawings and technical submittals.
Appears in 1 contract
Project Milestone-II. 2.1 Project Milestone-II shall occur on or before 6 (six) months from the Appointed Date (the “Project Milestone-II”) upon completion of 25% of civil construction works
2.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have completed building civil construction framing works upto terrace floor including headroom, fluid structure foundation and approval of all shop drawings and technical submittals.in value terms
Appears in 1 contract
Project Milestone-II. 2.1 Project Milestone-II shall occur on or before 6 (six) months from the Appointed Date (the “Project Milestone-II”) upon completion of 25% of civil construction works
2.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have completed building civil construction framing works upto terrace floor including headroom, fluid structure foundation and approval of all shop drawings and technical submittals.in value terms
Appears in 1 contract
Project Milestone-II. 2.1 Project Milestone-II shall occur on or before 6 (six) months from the Appointed Date (the “Project Milestone-II”) upon completion of 25% of civil construction works
2.2 Prior to the occurrence of Project Milestone-II, the Contractor shall have completed building civil construction framing works upto terrace floor including headroom, fluid structure foundation and approval of all shop drawings and technical submittalsin value terms.
Appears in 1 contract