Project Milestone-III Sample Clauses
The 'Project Milestone-III' clause defines the requirements and expectations for the third major phase or deliverable in a project timeline. It typically outlines the specific tasks, deliverables, or objectives that must be completed to achieve this milestone, such as submitting a progress report, delivering a prototype, or completing a key stage of work. This clause serves to track project progress, ensure accountability, and provide a clear checkpoint for evaluating whether the project is on schedule and meeting its goals.
Project Milestone-III. 2.1 Project Milestone-I shall occur on the date falling on the ____ ( ) day from the Appointed Date (“Project Milestone-III”).
2.2 Upon occurrence of Project Milestone-III, the Developer shall have expended not less than % ( per cent) of the total capital cost of Project Assets as set forth in the Financial Package and completed construction of:
c. d.
Project Milestone-III. 4.1 Project Milestone-III shall occur on the date falling on the 365th (three hundred and sixty fifth) day from the Appointed Date (the “Project Milestone-III”).
4.2 Prior to the occurrence of Project Milestone-III, the Concessionaire shall have expended not less than 75% (seventy-five per cent) of the total capital cost set forth in the Financial Package towards bus terminal component of Project.
Project Milestone-III. 4.1. Facility Owner shall achieve Commercial Operation Date on or before 8 (eight) months after the Effective Date.
Project Milestone-III. 3.1 Project Milestone-III shall occur on or before 11 (eleven) months from the Appointed Date (the “Project Milestone-III”) upon completion of 50% of civil construction works
3.2 Prior to the occurrence of Project Milestone-III, the Contractor shall have completed building civil construction works of Utility building basement, walls, columns. The Contractor shall have also completed beams and slab from ground to terrace level, block wall, water proofing, internal bridge, roof truss and covering works.
Project Milestone-III. Project Milestone-III shall occur on the date falling on the [1275th (one thousand two hundred and seventy fifth) day (43 Month) from the Compliance Date (the "Project Milestone-III").
Project Milestone-III. Project Milestone-III shall occur on or before 10 (ten) months from the Appointed Date (the “Project Milestone-III”) upon completion of 50% of civil construction works in value terms.
Project Milestone-III. 4.1. Facility Owner shall achieve Commercial Operation Date on or before 17 (seventeen) months from the date of execution of this Agreement.
Part 1: Key Personnel List
1.1 Facility Owner shall notify CEB of:
1.1.1 the identities of and contact details for the Plant Manager, who shall be responsible for general communications and contract management and the technical officer, who shall be responsible for technical and dispatching instructions and the maintenance of the Facility (“Facility Owner Operator”) at least 30 (thirty) days prior to the SCOD.
1.1.2 any changes from time to time in the identities of and contact details for such persons. Part 2: Communications
Project Milestone-III. 4.1 Project Milestone-III shall occur on the date falling on the 480th (four hundred and eightieth) day from the Appointed Date (the “Project Milestone-III”)
4.2 Prior to the occurrence of Project Milestone-III, the Concessionaire shall have commenced construction of all Project Facilities and expended not less than 75% (seventy five per cent) of the total capital cost set forth in the Financial Package.
4.3 Prior to the occurrence of Project Milestone-III, the Concessionaire shall have commenced construction of the Project and achieved 75% (seventy five per cent) physical progress.