Project Procurement Plan. Contractor shall produce a Project Procurement Plan for review by Owner within ninety (90) Days after Notice to Proceed, and Owner will provide review comments within ten (10) Business Days after receipt. The Project Procurement Plan will address, at a minimum: a. Inspection; b. Expediting; c. Supplier quality reports; d. Technical requirement compliance; e. Material control, marking, and certification; f. Packing, consolidation, importing; g. Transportation, handling, and storage; h. Warranties and guarantees; i. Vendor servicemen;
Appears in 12 contracts
Samples: Lump Sum Turnkey Agreement, Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.), Lump Sum Turnkey Agreement (Cheniere Energy Partners, L.P.)
Project Procurement Plan. Contractor shall produce a Project Procurement Plan for review by Owner within ninety (90) Days after Notice to Proceed, and Owner will provide review comments within ten (10) Business Days after receipt. The Project Procurement Plan will address, at a minimum:
a. Inspection; b. Identification of planned Equipment FAT and attendance;
b. Expediting;
c. Supplier quality reports;
d. Technical requirement compliance;
e. Material control, marking, and certification;
f. Packing, consolidation, importing;
g. Transportation, handling, and storage;
h. Warranties and guarantees;
i. Vendor servicemen;
Appears in 3 contracts
Samples: Fixed Price Separated Turnkey Agreement (Cheniere Corpus Christi Holdings, LLC), Fixed Price Separated Turnkey Agreement (Cheniere Energy Inc), Fixed Price Separated Turnkey Agreement (Corpus Christi Pipeline GP, LLC)
Project Procurement Plan. Contractor shall produce a Project Procurement Plan for review by Owner within ninety (90) Days after Notice to ProceedLNTP No. 1, and Owner will provide review comments within ten (10) Business Days after receipt. The Project Procurement Plan will address, at a minimum:
a. Inspection;
b. Expediting;
c. Supplier quality reports;
d. Technical requirement compliance;
e. Material control, marking, and certification;
f. Packing, consolidation, importing;
g. Transportation, handling, and storage;
h. Warranties and guarantees;
i. Vendor servicemen;
Appears in 1 contract
Samples: Lump Sum Turnkey Agreement (Sabine Pass Liquefaction, LLC)
Project Procurement Plan. Contractor shall produce a Project Procurement Plan for review by Owner within ninety (90) Days after Notice to Proceed, and Owner will provide review comments within ten (10) Business Days after receipt. The Project Procurement Plan will address, at a minimum:
a. Inspection;
b. Expediting;
c. • Inspection • Expediting • Supplier quality reports;
d. reports • Technical requirement compliance;
e. compliance • Material control, marking, and certification;
f. certification • Packing, consolidation, importing;
g. importing • Transportation, handling, and storage;
h. storage • Warranties and guarantees;
i. guarantees • Vendor servicemen;
Appears in 1 contract